§3132-B. Small transmission and distribution projects

For the purposes of this section, "small transmission project" means any proposed transmission line and associated infrastructure capable of operating at less than 69 kilovolts and projected to cost $5,000,000 or less.   [PL 2019, c. 298, §13 (NEW).]

1.  Planning study.  Each investor-owned transmission and distribution utility in this State shall annually complete and submit to the Office of the Public Advocate, for review by the nonwires alternative coordinator, a planning study for small transmission projects and distribution projects. In completing the planning study, an investor-owned transmission and distribution utility shall develop and use system planning models. The study must:

A. Analyze system needs for the next 5 years and provide a schedule of proposed projects and associated costs;   [PL 2019, c. 298, §13 (NEW).]

B. Describe system capacity and load by substation and circuit; and   [PL 2019, c. 298, §13 (NEW).]

C. Identify corresponding planned and anticipated growth-related investments.   [PL 2019, c. 298, §13 (NEW).]

After review of a planning study submitted under this subsection, the nonwires alternative coordinator may provide comments or recommendations, which may include recommendations to achieve the policy goals established in section 3143. An investor-owned transmission and distribution utility may, at its discretion, incorporate recommendations on a planning study made by the nonwires alternative coordinator. Failure to incorporate recommendations made by the nonwires alternative coordinator may not result in a presumption of imprudence.

[PL 2019, c. 298, §13 (NEW).]

2.  Nonwires alternatives investigation.  Except as provided in subsection 3, for a proposed project presented in a planning study under subsection 1, the nonwires alternative coordinator:

A. Shall investigate nonwires alternatives if the project is a small transmission project or is a distribution project estimated to cost $500,000 or more; and   [PL 2019, c. 298, §13 (NEW).]

B. May investigate nonwires alternatives if the project is a distribution project estimated to cost less than $500,000 and, in the judgment of the nonwires alternative coordinator, there is a reasonable likelihood that a nonwires alternative would be more cost-effective than the proposed distribution project.   [PL 2019, c. 298, §13 (NEW).]

An investigation of nonwires alternatives under this subsection must be conducted in accordance with section 3132‑C.

[PL 2019, c. 298, §13 (NEW).]

3.  Excluded projects; criteria.  The commission, by rule, shall develop criteria to exclude from investigation by the nonwires alternative coordinator small transmission projects and distribution projects best suited to transmission and distribution investments, including but not limited to projects that are:

A. Necessary for redundant supply to a radial load;   [PL 2019, c. 298, §13 (NEW).]

B. Necessary to address maintenance, asset condition or safety needs;   [PL 2019, c. 298, §13 (NEW).]

C. Necessary to address stability or short circuit problems; or   [PL 2019, c. 298, §13 (NEW).]

D. Required to be in service within one year based on the controlling load forecast.   [PL 2019, c. 298, §13 (NEW).]

[PL 2019, c. 298, §13 (NEW).]

4.  Nonwires alternatives recommendations.  Based on the investigation under subsection 2, the nonwires alternative coordinator shall make recommendations to the investor-owned transmission and distribution utility regarding nonwires alternatives to proposed small transmission projects and distribution projects. The nonwires alternative coordinator and the utility shall attempt to reach a good faith agreement regarding the adoption of nonwires alternatives that are most cost-effective. If agreement is reached, the utility shall pursue the agreed-upon nonwires alternatives. If there is no agreement, the utility shall petition the commission to resolve the dispute.

[PL 2019, c. 298, §13 (NEW).]

5.  Dispute resolution.  In responding to a petition by an investor-owned transmission and distribution utility pursuant to subsection 4, the commission shall review the planning study prepared under subsection 1 and the recommendations of the nonwires alternative coordinator under subsection 4. In resolving the dispute, the commission shall give preference to nonwires alternatives that are identified as able to address the identified need for the proposed small transmission project or distribution project and are most cost-effective. Of the identified nonwires alternatives, the commission shall give preference to the lowest-cost nonwires alternatives. When the costs to ratepayers in this State of the identified nonwires alternatives are reasonably equal, the commission shall give preference to the nonwires alternatives that produce the lowest amount of local air emissions, including greenhouse gas emissions.

[PL 2019, c. 298, §13 (NEW).]

SECTION HISTORY

PL 2019, c. 298, §13 (NEW).

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
35-A §3132-B. Small transmission and distribution projects