35-A §3132-A. Construction of transmission projects prohibited without approval of the commission

35-A ME Rev Stat § 3132-A (2019) (N/A)
Copy with citation
Copy as parenthetical citation

§3132-A. Construction of transmission projects prohibited without approval of the commission

A person may not construct any transmission project without approval from the commission. For the purposes of this section, "transmission project" means any proposed transmission line and its associated infrastructure capable of operating at less than 69 kilovolts and projected to cost in excess of $5,000,000.   [PL 2019, c. 298, §12 (AMD).]

1.  Submission requirement.  A person that proposes to undertake in the State a transmission project must provide the commission with a description of the need for the proposed transmission project.

A. [PL 2017, c. 201, §5 (RP).]

B. [PL 2017, c. 201, §5 (RP).]

[PL 2017, c. 201, §5 (AMD).]

1-A.  Nonwires alternatives investigation; consideration.  In considering whether to approve or disapprove all or portions of a proposed transmission project pursuant to subsection 2, the commission shall, for a transmission project proposed by an investor-owned transmission and distribution utility, consider the results and recommendations of an investigation by the nonwires alternative coordinator conducted in accordance with section 3132‑C.

[PL 2019, c. 298, §12 (AMD).]

2.  Commission approval of a proposed transmission project; nontransmission alternatives.  In order for a transmission project to be approved, the commission must consider whether the identified need over the effective life of the proposed transmission project can be reliably and more cost-effectively met using nontransmission alternatives. In its review and consideration of nontransmission alternatives, as required by subsection 1‑A, the commission shall give preference to nontransmission alternatives that have been identified as able to address the identified need for the proposed transmission project most cost-effectively. When the cost-effectiveness of the identified nontransmission alternatives are reasonably equal, the commission shall give preference to the alternatives that produce the lowest amount of local air emissions, including greenhouse gas emissions.

[PL 2019, c. 298, §12 (AMD).]

3.  Exception.  A transmission project that is constructed, owned and operated by a generator of electricity solely for the purpose of electrically and physically interconnecting the generator to the transmission system of a transmission and distribution utility is not subject to this section.

[PL 2013, c. 369, Pt. C, §8 (NEW).]

SECTION HISTORY

PL 2013, c. 369, Pt. C, §8 (NEW). PL 2017, c. 201, §§5, 6 (AMD). PL 2019, c. 298, §12 (AMD).

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.