The Secretary of Energy shall, during each even-numbered year beginning in 2016, develop and subsequently carry out a plan for the activities of the Department of Energy relating to the deactivation and decommissioning of nonoperational defense nuclear facilities.

The plan required by subsection (a) shall include the following:

(1) A list of nonoperational defense nuclear facilities, prioritized for deactivation and decommissioning based on the potential to reduce risks to human health, property, or the environment and to maximize cost savings.

An assessment of the life cycle costs of each nonoperational defense nuclear facility during the period beginning on the date on which the plan is submitted under subsection (d) and ending on the earlier of—

(A) the date that is 25 years after the date on which the plan is submitted; or

(B) the estimated date for deactivation and decommissioning of the facility.

(3) An estimate of the cost and time needed to deactivate and decommission each nonoperational defense nuclear facility.

(4) A schedule for when the Office of Environmental Management will accept each nonoperational defense nuclear facility for deactivation and decommissioning.

An estimate of costs that could be avoided by—

(A) accelerating the cleanup of nonoperational defense nuclear facilities; or

(B) other means, such as reusing such facilities for another purpose.

The Secretary shall, during 2016, develop and subsequently carry out a plan under which the Administrator shall transfer, by March 31, 2019, to the Assistant Secretary for Environmental Management the responsibility for decontaminating and decommissioning facilities of the Administration that the Secretary determines—

(1) are nonoperational as of September 30, 2015; and

(2) meet the requirements of the Office of Environmental Management for such transfer.

Not later than March 31 of each even-numbered year beginning in 2016, the Secretary shall submit to the appropriate congressional committees a report that includes—

(1) the plan required by subsection (a);

(2) a description of the deactivation and decommissioning actions expected to be taken during the following fiscal year pursuant to the plan;

(3) in the case of the report submitting [1] during 2016, the plan required by subsection (c); and

(4) in the case of a report submitted during 2018 or any year thereafter, a description of the deactivation and decommissioning actions taken at each nonoperational defense nuclear facility during the preceding fiscal year.

The requirements of this section shall terminate after the submission to the appropriate congressional committees of the report required by subsection (d) to be submitted not later than March 31, 2026.

In this section:

The term “appropriate congressional committees” means—

(A) the congressional defense committees; and

(B) the Committee on Energy and Natural Resources of the Senate and the Committee on Energy and Commerce of the House of Representatives.

The term “life cycle costs”, with respect to a facility, means—

(A) the present and future costs of all resources and associated cost elements required to develop, produce, deploy, or sustain the facility; and

(B) the present and future costs to deactivate, decommission, and deconstruct the facility.

(3) The term “nonoperational defense nuclear facility” means a production facility or utilization facility (as those terms are defined in section 2014 of title 42) under the control or jurisdiction of the Secretary of Energy and operated for national security purposes that is no longer needed for the mission of the Department of Energy, including the National Nuclear Security Administration.

(Pub. L. 107–314, div. D, title XLIV, § 4423, as added Pub. L. 114–92, div. C, title XXXI, § 3133(a), Nov. 25, 2015, 129 Stat. 1205.)

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
§ 2603. Plan for deactivation and decommissioning of nonoperational defense nuclear facilities