36.70C.130 Standards for granting relief—Renewable resource projects within energy overlay zones.

WA Rev Code § 36.70C.130 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

RCW 36.70C.130 Standards for granting relief—Renewable resource projects within energy overlay zones.

(1) The superior court, acting without a jury, shall review the record and such supplemental evidence as is permitted under RCW 36.70C.120. The court may grant relief only if the party seeking relief has carried the burden of establishing that one of the standards set forth in (a) through (f) of this subsection has been met. The standards are:

(a) The body or officer that made the land use decision engaged in unlawful procedure or failed to follow a prescribed process, unless the error was harmless;

(b) The land use decision is an erroneous interpretation of the law, after allowing for such deference as is due the construction of a law by a local jurisdiction with expertise;

(c) The land use decision is not supported by evidence that is substantial when viewed in light of the whole record before the court;

(d) The land use decision is a clearly erroneous application of the law to the facts;

(e) The land use decision is outside the authority or jurisdiction of the body or officer making the decision; or

(f) The land use decision violates the constitutional rights of the party seeking relief.

(2) In order to grant relief under this chapter, it is not necessary for the court to find that the local jurisdiction engaged in arbitrary and capricious conduct. A grant of relief by itself may not be deemed to establish liability for monetary damages or compensation.

(3) Land use decisions made by a local jurisdiction concerning renewable resource projects within a county energy overlay zone are presumed to be reasonable if they are in compliance with the requirements and standards established by local ordinance for that zone. However, for land use decisions concerning wind power generation projects, either:

(a) The local ordinance for that zone is consistent with the department of fish and wildlife's wind power guidelines; or

(b) The local jurisdiction prepared an environmental impact statement under chapter 43.21C RCW on the energy overlay zone; and

(i) The local ordinance for that zone requires project mitigation, as addressed in the environmental impact statement and consistent with local, state, and federal law;

(ii) The local ordinance for that zone requires site specific fish and wildlife and cultural resources analysis; and

(iii) The local jurisdiction has adopted an ordinance that addresses critical areas under chapter 36.70A RCW.

(4) If a local jurisdiction has taken action and adopted local ordinances consistent with subsection (3)(b) of this section, then wind power generation projects permitted consistently with the energy overlay zone are deemed to have adequately addressed their environmental impacts as required under chapter 43.21C RCW.

[ 2009 c 419 § 2; 1995 c 347 § 714.]

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
36.70C.130 Standards for granting relief—Renewable resource projects within energy overlay zones.