§ 8506. Renewable energy plant; telecommunications facility; appeals

(a) Within 30 days of the date of the act or decision, any person aggrieved by an act or decision of the Secretary, under the provisions of law listed in section 8503 of this title, or any party by right may appeal to the Public Utility Commission if the act or decision concerns a renewable energy plant for which a certificate of public good is required under 30 V.S.A. § 248 or a telecommunications facility for which the applicant has applied or has served notice under 30 V.S.A. § 248a(e) that it will apply for approval under 30 V.S.A. § 248a. This section shall not apply to a facility that is subject to section 1004 (dams before the Federal Energy Regulatory Commission) or 1006 (certification of hydroelectric projects) or chapter 43 (dams) of this title. This section shall not apply to an appeal of an act or decision of the Secretary regarding a telecommunications facility made on or after July 1, 2017.

(b) For the purpose of this section, "Commission," "plant," and "renewable energy" have the same meaning as under 30 V.S.A. § 8002, and "telecommunications facility" has the same meaning as under 30 V.S.A. § 248a.

(c) The provisions of subdivisions 8504(c)(2) (notice of appeal), (d)(2) (participation before the Secretary), and (f)(1)(A) (automatic stays of certain permits), and subsections 8504(j) (appeals under a general permit), (n) (intervention), and (p) (administrative record) of this title shall apply to appeals under this section except that, with respect to subsection (p), the Secretary shall transfer a certified copy of the administrative record to the Commission.

(d) The Public Utility Commission may consolidate or coordinate appeals under this section with each other and with proceedings under 30 V.S.A. §§ 248 and 248a, where those appeals and proceedings all relate to the same project, unless such consolidation or coordination would be clearly unreasonable. In such a consolidated proceeding, the Commission's decision may be issued as a single order that includes the necessary findings of fact and conclusions of law and, if the decision is to approve the plant or facility, any and all conditions of approval. This authority to consolidate or coordinate appeals and proceedings shall not confer authority to alter the substantive standards at issue in an appeal or proceeding.

(e) In an appeal under this section, the Public Utility Commission, applying the substantive standards that were applicable before the Secretary, shall hold a de novo hearing on those issues which have been appealed. In such an appeal, the Commission shall give the same weight and consideration to prior decisions of the Environmental Division and of the entities described in subsection 8504(m) (precedent) of this title as the Commission gives to its prior decisions.

(f) 30 V.S.A. §§ 9 (court of record), 10 (service of process), 11 (pleadings; rules of practice; findings of fact), and 12 (review by Supreme Court) shall apply to appeals under this section. (Added 2009, No. 159 (Adj. Sess.), § 18, eff. June 4, 2010; amended 2011, No. 53, § 6, eff. May 27, 2011; 2013, No. 190 (Adj. Sess.), § 21, eff. June 16, 2014; 2013, No. 199 (Adj. Sess.), § 31; 2015, No. 150 (Adj. Sess.), § 5a, eff. Jan. 1, 2018.)

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
§ 8506 Renewable energy plant; telecommunications facility; appeals