(1) (a) Within 48 hours of the receipt of the notice required by Section 54-8a-4, the operator shall: (i) mark the location of its underground facilities in the area of the proposed excavation; or (ii) notify the excavator, by telephonic or electronic message or indication at the excavation site, that the operator does not have any underground facility in the area of the proposed excavation. (b) The underground facility shall be marked using as a guideline the then-existing Uniform Color Code and Marking Guidelines, Appendix B, published by the Common Ground Alliance, as amended in the current version of the excavators' guide published by the statewide association established in Section 54-8a-9.

(a) Within 48 hours of the receipt of the notice required by Section 54-8a-4, the operator shall: (i) mark the location of its underground facilities in the area of the proposed excavation; or (ii) notify the excavator, by telephonic or electronic message or indication at the excavation site, that the operator does not have any underground facility in the area of the proposed excavation.

(i) mark the location of its underground facilities in the area of the proposed excavation; or

(ii) notify the excavator, by telephonic or electronic message or indication at the excavation site, that the operator does not have any underground facility in the area of the proposed excavation.

(b) The underground facility shall be marked using as a guideline the then-existing Uniform Color Code and Marking Guidelines, Appendix B, published by the Common Ground Alliance, as amended in the current version of the excavators' guide published by the statewide association established in Section 54-8a-9.

(2) (a) The operator is not required to mark the underground facilities within 48 hours if: (i) the proposed excavation: (A) is not identified in accordance with Subsection 54-8a-4(2) or is not marked as provided in Subsection 54-8a-4(3); (B) is located in a remote area; (C) is an extensive excavation; or (D) presents other constraints that make it unreasonably difficult for the operator to comply with the marking requirements of this section; or (ii) the operator is not able to readily locate the underground facilities from the surface with standard underground detection devices. (b) If the operator cannot proceed with the marking because of a situation described in Subsection (2)(a), the operator shall contact the excavator within 48 hours after the excavator's notice of excavation or request for a location request assignment made in accordance with Section 54-8a-4 and: (i) request a meeting at the proposed excavation site or some other mutually agreed upon location; or (ii) at the operator's discretion, contact the excavator and request the proposed excavation site be outlined in accordance with Subsection 54-8a-4(3). (c) For a situation described under Subsection (2)(a)(i), the meeting or completed outlining of the proposed excavation site constitutes the beginning of a new 48-hour period within which the operator must begin marking the underground facilities. (d) (i) For the situation described under Subsection (2)(a)(ii), the excavator and operator shall agree on a plan of excavation designed to prevent damage to the operator's underground facility. (ii) Notwithstanding the agreement, the excavator shall proceed in a manner that is reasonably calculated to avoid damage to the underground facility. (e) (i) An operator need not mark or locate an underground facility the operator does not own. (ii) An underground facility under Subsection (2)(e)(i) includes a water or sewer lateral or a facility running from a house to a garage or outbuilding. (f) (i) An operator may mark the location of a known facility connected to the operator's facilities that is not owned or operated by the operator. (ii) Marking a known facility under Subsection (2)(f)(i) imposes no liability on the operator for the accuracy of the marking.

(a) The operator is not required to mark the underground facilities within 48 hours if: (i) the proposed excavation: (A) is not identified in accordance with Subsection 54-8a-4(2) or is not marked as provided in Subsection 54-8a-4(3); (B) is located in a remote area; (C) is an extensive excavation; or (D) presents other constraints that make it unreasonably difficult for the operator to comply with the marking requirements of this section; or (ii) the operator is not able to readily locate the underground facilities from the surface with standard underground detection devices.

(i) the proposed excavation: (A) is not identified in accordance with Subsection 54-8a-4(2) or is not marked as provided in Subsection 54-8a-4(3); (B) is located in a remote area; (C) is an extensive excavation; or (D) presents other constraints that make it unreasonably difficult for the operator to comply with the marking requirements of this section; or

(A) is not identified in accordance with Subsection 54-8a-4(2) or is not marked as provided in Subsection 54-8a-4(3);

(B) is located in a remote area;

(C) is an extensive excavation; or

(D) presents other constraints that make it unreasonably difficult for the operator to comply with the marking requirements of this section; or

(ii) the operator is not able to readily locate the underground facilities from the surface with standard underground detection devices.

(b) If the operator cannot proceed with the marking because of a situation described in Subsection (2)(a), the operator shall contact the excavator within 48 hours after the excavator's notice of excavation or request for a location request assignment made in accordance with Section 54-8a-4 and: (i) request a meeting at the proposed excavation site or some other mutually agreed upon location; or (ii) at the operator's discretion, contact the excavator and request the proposed excavation site be outlined in accordance with Subsection 54-8a-4(3).

(i) request a meeting at the proposed excavation site or some other mutually agreed upon location; or

(ii) at the operator's discretion, contact the excavator and request the proposed excavation site be outlined in accordance with Subsection 54-8a-4(3).

(c) For a situation described under Subsection (2)(a)(i), the meeting or completed outlining of the proposed excavation site constitutes the beginning of a new 48-hour period within which the operator must begin marking the underground facilities.

(d) (i) For the situation described under Subsection (2)(a)(ii), the excavator and operator shall agree on a plan of excavation designed to prevent damage to the operator's underground facility. (ii) Notwithstanding the agreement, the excavator shall proceed in a manner that is reasonably calculated to avoid damage to the underground facility.

(i) For the situation described under Subsection (2)(a)(ii), the excavator and operator shall agree on a plan of excavation designed to prevent damage to the operator's underground facility.

(ii) Notwithstanding the agreement, the excavator shall proceed in a manner that is reasonably calculated to avoid damage to the underground facility.

(e) (i) An operator need not mark or locate an underground facility the operator does not own. (ii) An underground facility under Subsection (2)(e)(i) includes a water or sewer lateral or a facility running from a house to a garage or outbuilding.

(i) An operator need not mark or locate an underground facility the operator does not own.

(ii) An underground facility under Subsection (2)(e)(i) includes a water or sewer lateral or a facility running from a house to a garage or outbuilding.

(f) (i) An operator may mark the location of a known facility connected to the operator's facilities that is not owned or operated by the operator. (ii) Marking a known facility under Subsection (2)(f)(i) imposes no liability on the operator for the accuracy of the marking.

(i) An operator may mark the location of a known facility connected to the operator's facilities that is not owned or operated by the operator.

(ii) Marking a known facility under Subsection (2)(f)(i) imposes no liability on the operator for the accuracy of the marking.

(3) Each marking is valid for not more than 14 calendar days from the date notice is given.

(4) If multiple lines exist: (a) the markings must indicate the number of lines; or (b) all lines must be marked.

(a) the markings must indicate the number of lines; or

(b) all lines must be marked.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 5 - Marking of underground facilities.