Section 26 - Notice that service from underground facilities is available -- Consequences of failure to convert overhead facilities.

UT Code § 54-8-26 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) (a) If service from the underground public utility is to be made available to all or part of an improvement district area, the governing body of the county or municipality that created the district shall mail a notice to each owner of real property served from existing overhead facilities stating that: (i) conversion of all facilities owned within the improvement district by a public utility from overhead to underground to the point of delivery is proceeding; (ii) the property owner is responsible for the changes in the service entrance equipment located on the property to accommodate the conversion of the applicable public utility's facilities from overhead to underground at the point of delivery; and (iii) each owner shall coordinate with the applicable public utility to make the conversion from overhead to underground service. (b) In addition to improvement district assessments, the property owner shall bear the expense of the conversion from overhead to underground described in Subsections (1)(a)(ii) and (iii). (c) Each conversion of overhead facilities to underground facilities shall comply with all applicable state and local laws, ordinances, rules, and regulations, and with all tariffs of the applicable public utility. (d) The public utility or its contractor shall perform the necessary construction to the point of delivery, unless the public utility authorizes another to perform the construction.

(a) If service from the underground public utility is to be made available to all or part of an improvement district area, the governing body of the county or municipality that created the district shall mail a notice to each owner of real property served from existing overhead facilities stating that: (i) conversion of all facilities owned within the improvement district by a public utility from overhead to underground to the point of delivery is proceeding; (ii) the property owner is responsible for the changes in the service entrance equipment located on the property to accommodate the conversion of the applicable public utility's facilities from overhead to underground at the point of delivery; and (iii) each owner shall coordinate with the applicable public utility to make the conversion from overhead to underground service.

(i) conversion of all facilities owned within the improvement district by a public utility from overhead to underground to the point of delivery is proceeding;

(ii) the property owner is responsible for the changes in the service entrance equipment located on the property to accommodate the conversion of the applicable public utility's facilities from overhead to underground at the point of delivery; and

(iii) each owner shall coordinate with the applicable public utility to make the conversion from overhead to underground service.

(b) In addition to improvement district assessments, the property owner shall bear the expense of the conversion from overhead to underground described in Subsections (1)(a)(ii) and (iii).

(c) Each conversion of overhead facilities to underground facilities shall comply with all applicable state and local laws, ordinances, rules, and regulations, and with all tariffs of the applicable public utility.

(d) The public utility or its contractor shall perform the necessary construction to the point of delivery, unless the public utility authorizes another to perform the construction.

(2) (a) Failure to have the property owner's service entrance equipment described in Subsection (1)(a)(ii) converted to accommodate underground service within the time that the governing body specifies in writing shall be considered as the property owner's consent to and grant of a construction easement to the county or municipality and as express authority to the county or municipality to arrange for qualified persons to enter upon the lot or parcel for the purpose of making the required changes. (b) A construction easement under Subsection (2)(a) terminates upon completion of the conversion of overhead facilities to underground.

(a) Failure to have the property owner's service entrance equipment described in Subsection (1)(a)(ii) converted to accommodate underground service within the time that the governing body specifies in writing shall be considered as the property owner's consent to and grant of a construction easement to the county or municipality and as express authority to the county or municipality to arrange for qualified persons to enter upon the lot or parcel for the purpose of making the required changes.

(b) A construction easement under Subsection (2)(a) terminates upon completion of the conversion of overhead facilities to underground.

(3) If the county or municipality arranges for the conversion of the service entrance equipment, all county, municipal, and public utility costs and expenses of the conversion, including the engineering, legal, advertising, and incidental expenses, shall be assessed against the property upon which the service entrance equipment was converted and become a lien upon the property served.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 26 - Notice that service from underground facilities is available -- Consequences of failure to convert overhead facilities.