(1) If the board decides that a facility permitted to be constructed by a local government is subject to requirements or conditions that impose an estimated excess cost but do not impair the provision of safe, reliable, and adequate service to customers of the public utility, the local government shall, within 20 days following the decision of the board, determine whether it will impose the requirement or conditions imposing an estimated excess cost or issue the permit, authorization, approval, exception, or waiver without the requirements or conditions imposing an estimated excess cost.

(2) If the board decides that a facility should be constructed that the local government has prohibited, the local government shall, within 60 days following the decision of the board, issue the permit, authorization, approval, exception, or waiver consistent with the decision of the board.

(3) The local government may impose requirements or conditions pursuant to its zoning, subdivision, or building code regulations if: (a) the requirements or conditions do not impair safe, reliable, and adequate service to the customers of the utility; and (b) the local government enters into an agreement with the public utility within the 20-day time limit specified by Subsection (1) or the 60-day time limit specified by Subsection (2) to pay for the actual excess cost to the public utility, except any actual excess costs specified in Subsection 54-14-201(2)(a) or (2)(b), at least 30 days before the date construction of the facility should commence.

(a) the requirements or conditions do not impair safe, reliable, and adequate service to the customers of the utility; and

(b) the local government enters into an agreement with the public utility within the 20-day time limit specified by Subsection (1) or the 60-day time limit specified by Subsection (2) to pay for the actual excess cost to the public utility, except any actual excess costs specified in Subsection 54-14-201(2)(a) or (2)(b), at least 30 days before the date construction of the facility should commence.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 306 - Action required of local government following board decision.