LegalFix

Section 202 - Public utility to provide standard cost and estimated excess cost.

UT Code § 54-14-202 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) (a) A public utility shall provide the information described in Subsection (1)(b) if a local government: (i) is considering imposing requirements or conditions on construction of a facility that may result in an estimated excess cost and requests that the public utility provide the estimated excess cost; or (ii) recommends an alternative to the public utility's proposed high voltage transmission line corridor in accordance with the provisions of Title 54, Chapter 18, Siting of High Voltage Power Line Act. (b) Subject to Subsection (1)(a), a public utility shall provide to the local government: (i) (A) the estimated standard cost of the facility; and (B) the estimated excess cost of the facility if constructed in accordance with local government requirements or conditions; and (ii) the estimated cost of the alternative line corridor proposed by a local government provided that all affected land use authorities agree to the alternative line corridor proposed by the local government.

(a) A public utility shall provide the information described in Subsection (1)(b) if a local government: (i) is considering imposing requirements or conditions on construction of a facility that may result in an estimated excess cost and requests that the public utility provide the estimated excess cost; or (ii) recommends an alternative to the public utility's proposed high voltage transmission line corridor in accordance with the provisions of Title 54, Chapter 18, Siting of High Voltage Power Line Act.

(i) is considering imposing requirements or conditions on construction of a facility that may result in an estimated excess cost and requests that the public utility provide the estimated excess cost; or

(ii) recommends an alternative to the public utility's proposed high voltage transmission line corridor in accordance with the provisions of Title 54, Chapter 18, Siting of High Voltage Power Line Act.

(b) Subject to Subsection (1)(a), a public utility shall provide to the local government: (i) (A) the estimated standard cost of the facility; and (B) the estimated excess cost of the facility if constructed in accordance with local government requirements or conditions; and (ii) the estimated cost of the alternative line corridor proposed by a local government provided that all affected land use authorities agree to the alternative line corridor proposed by the local government.

(i) (A) the estimated standard cost of the facility; and (B) the estimated excess cost of the facility if constructed in accordance with local government requirements or conditions; and

(A) the estimated standard cost of the facility; and

(B) the estimated excess cost of the facility if constructed in accordance with local government requirements or conditions; and

(ii) the estimated cost of the alternative line corridor proposed by a local government provided that all affected land use authorities agree to the alternative line corridor proposed by the local government.

(2) If a public utility does not provide the information as described in Subsection (1), the local government may: (a) appeal to the board; and (b) request that the board review the information provided by the public utility.

(a) appeal to the board; and

(b) request that the board review the information provided by the public utility.

(3) (a) If the board finds that the public utility has failed to provide the standard costs and estimated excess costs in accordance with the provisions of Subsection (1), the board may request additional information from the public utility. (b) In accordance with Subsection (3)(a), a public utility shall provide any information requested by the board within 30 days of the day that the request was made. (c) If a public utility fails to comply with Subsections (3)(a) and (b), the board may suspend issuing its written decision in accordance with Section 54-14-305 for 30 days after the day on which the public utility provides the information requested under Subsection (3)(a).

(a) If the board finds that the public utility has failed to provide the standard costs and estimated excess costs in accordance with the provisions of Subsection (1), the board may request additional information from the public utility.

(b) In accordance with Subsection (3)(a), a public utility shall provide any information requested by the board within 30 days of the day that the request was made.

(c) If a public utility fails to comply with Subsections (3)(a) and (b), the board may suspend issuing its written decision in accordance with Section 54-14-305 for 30 days after the day on which the public utility provides the information requested under Subsection (3)(a).

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 202 - Public utility to provide standard cost and estimated excess cost.