Section 701 - Action to enforce lien -- Time for filing action -- Notice of pendency of action -- Action involving a residence.

UT Code § 38-1a-701 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) As used in this section: (a) "Owner" has the same meaning as defined in Section 38-11-102. (b) "Residence" has the same meaning as defined in Section 38-11-102.

(a) "Owner" has the same meaning as defined in Section 38-11-102.

(b) "Residence" has the same meaning as defined in Section 38-11-102.

(2) In order to enforce a preconstruction lien or construction lien, a claimant shall file an action to enforce the lien: (a) except as provided in Subsection (2)(b), within 180 days after the day on which the claimant files: (i) a notice of preconstruction lien under Section 38-1a-402, for a preconstruction lien; or (ii) a notice of construction lien under Section 38-1a-502, for a construction lien; or (b) if an owner files for protection under the bankruptcy laws of the United States before the expiration of the 180-day period under Subsection (2)(a), within 90 days after the automatic stay under the bankruptcy proceeding is lifted or expires.

(a) except as provided in Subsection (2)(b), within 180 days after the day on which the claimant files: (i) a notice of preconstruction lien under Section 38-1a-402, for a preconstruction lien; or (ii) a notice of construction lien under Section 38-1a-502, for a construction lien; or

(i) a notice of preconstruction lien under Section 38-1a-402, for a preconstruction lien; or

(ii) a notice of construction lien under Section 38-1a-502, for a construction lien; or

(b) if an owner files for protection under the bankruptcy laws of the United States before the expiration of the 180-day period under Subsection (2)(a), within 90 days after the automatic stay under the bankruptcy proceeding is lifted or expires.

(3) (a) (i) Within the time period provided in Subsection (2) for filing an action, a claimant shall file for record with each applicable county recorder a notice of the pendency of the action, in the manner provided for actions affecting the title or right to possession of real property. (ii) If a claimant fails to file for record a notice of the pendency of the action, as required in Subsection (3)(a)(i), the preconstruction lien or construction lien, as applicable, is void, except as to persons who have been made parties to the action and persons having actual knowledge of the commencement of the action. (b) The burden of proof is upon the claimant and those claiming under the claimant to show actual knowledge under Subsection (3)(a)(ii).

(a) (i) Within the time period provided in Subsection (2) for filing an action, a claimant shall file for record with each applicable county recorder a notice of the pendency of the action, in the manner provided for actions affecting the title or right to possession of real property. (ii) If a claimant fails to file for record a notice of the pendency of the action, as required in Subsection (3)(a)(i), the preconstruction lien or construction lien, as applicable, is void, except as to persons who have been made parties to the action and persons having actual knowledge of the commencement of the action.

(i) Within the time period provided in Subsection (2) for filing an action, a claimant shall file for record with each applicable county recorder a notice of the pendency of the action, in the manner provided for actions affecting the title or right to possession of real property.

(ii) If a claimant fails to file for record a notice of the pendency of the action, as required in Subsection (3)(a)(i), the preconstruction lien or construction lien, as applicable, is void, except as to persons who have been made parties to the action and persons having actual knowledge of the commencement of the action.

(b) The burden of proof is upon the claimant and those claiming under the claimant to show actual knowledge under Subsection (3)(a)(ii).

(4) (a) A preconstruction lien or construction lien is automatically and immediately void if an action to enforce the lien is not filed within the time required by this section. (b) Notwithstanding Section 78B-2-111, a court has no subject matter jurisdiction to adjudicate a preconstruction or construction lien that becomes void under Subsection (4)(a).

(a) A preconstruction lien or construction lien is automatically and immediately void if an action to enforce the lien is not filed within the time required by this section.

(b) Notwithstanding Section 78B-2-111, a court has no subject matter jurisdiction to adjudicate a preconstruction or construction lien that becomes void under Subsection (4)(a).

(5) This section may not be interpreted to impair or affect the right of any person to whom a debt may be due for any preconstruction service or construction work to maintain a personal action to recover the debt.

(6) (a) If a claimant files an action to enforce a preconstruction or construction lien involving a residence, the claimant shall include with the service of the complaint on the owner of the residence: (i) instructions to the owner of the residence relating to the owner's rights under Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act; and (ii) a form to enable the owner of the residence to specify the grounds upon which the owner may exercise available rights under Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act. (b) The instructions and form required by Subsection (6)(a) shall meet the requirements established by the division by rule. (c) If a claimant fails to provide to the owner of the residence the instructions and form required by Subsection (6)(a), the claimant is barred from maintaining or enforcing the preconstruction or construction lien upon the residence. (d) A court shall stay an action to determine the rights and liabilities of an owner of a residence under this chapter, Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act, and Title 14, Chapter 2, Private Contracts, until after the owner is given a reasonable period of time to: (i) establish compliance with Subsections 38-11-204(4)(a) and (4)(b) through an informal proceeding, as set forth in Title 63G, Chapter 4, Administrative Procedures Act, commenced at the division within 30 days after the owner is served with summons in the foreclosure action; and (ii) obtain a certificate of compliance or denial of certificate of compliance, as defined in Section 38-11-102. (e) An owner applying for a certificate of compliance under Subsection (6)(d) shall send by certified mail to all claimants: (i) a copy of the application for a certificate of compliance; and (ii) all materials filed in connection with the application. (f) The division shall notify all claimants listed in an owner's application for a certificate of compliance under Subsection (6)(d) of the issuance or denial of a certificate of compliance.

(a) If a claimant files an action to enforce a preconstruction or construction lien involving a residence, the claimant shall include with the service of the complaint on the owner of the residence: (i) instructions to the owner of the residence relating to the owner's rights under Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act; and (ii) a form to enable the owner of the residence to specify the grounds upon which the owner may exercise available rights under Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act.

(i) instructions to the owner of the residence relating to the owner's rights under Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act; and

(ii) a form to enable the owner of the residence to specify the grounds upon which the owner may exercise available rights under Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act.

(b) The instructions and form required by Subsection (6)(a) shall meet the requirements established by the division by rule.

(c) If a claimant fails to provide to the owner of the residence the instructions and form required by Subsection (6)(a), the claimant is barred from maintaining or enforcing the preconstruction or construction lien upon the residence.

(d) A court shall stay an action to determine the rights and liabilities of an owner of a residence under this chapter, Title 38, Chapter 11, Residence Lien Restriction and Lien Recovery Fund Act, and Title 14, Chapter 2, Private Contracts, until after the owner is given a reasonable period of time to: (i) establish compliance with Subsections 38-11-204(4)(a) and (4)(b) through an informal proceeding, as set forth in Title 63G, Chapter 4, Administrative Procedures Act, commenced at the division within 30 days after the owner is served with summons in the foreclosure action; and (ii) obtain a certificate of compliance or denial of certificate of compliance, as defined in Section 38-11-102.

(i) establish compliance with Subsections 38-11-204(4)(a) and (4)(b) through an informal proceeding, as set forth in Title 63G, Chapter 4, Administrative Procedures Act, commenced at the division within 30 days after the owner is served with summons in the foreclosure action; and

(ii) obtain a certificate of compliance or denial of certificate of compliance, as defined in Section 38-11-102.

(e) An owner applying for a certificate of compliance under Subsection (6)(d) shall send by certified mail to all claimants: (i) a copy of the application for a certificate of compliance; and (ii) all materials filed in connection with the application.

(i) a copy of the application for a certificate of compliance; and

(ii) all materials filed in connection with the application.

(f) The division shall notify all claimants listed in an owner's application for a certificate of compliance under Subsection (6)(d) of the issuance or denial of a certificate of compliance.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 701 - Action to enforce lien -- Time for filing action -- Notice of pendency of action -- Action involving a residence.