Section 402 - Notice of preconstruction lien -- Requirements.

UT Code § 38-1a-402 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) Within 90 days after completing a preconstruction service for which a claimant is not paid in full, a claimant who desires to claim a preconstruction lien shall submit for recording with each applicable county recorder a notice of preconstruction lien.

(2) A claimant who fails to submit a notice of preconstruction lien as provided in Subsection (1) may not claim a preconstruction lien.

(3) (a) A notice of preconstruction service lien shall include: (i) the claimant's name, mailing address, and telephone number; (ii) a statement that the claimant claims a preconstruction lien; (iii) the date the claimant's notice of preconstruction service was filed; (iv) the name of the person that employed the claimant; (v) a general description of the preconstruction service provided by the claimant; (vi) the date that the claimant last provided preconstruction service; (vii) the name, if known, of the reputed owner or, if not known, the name of the record owner; (viii) a description of the project property sufficient for identification; (ix) the principal amount, excluding interest, costs, and attorney fees, claimed by the claimant; (x) the claimant's signature or the signature of the claimant's authorized agent; (xi) an acknowledgment or certificate as required under Title 57, Chapter 3, Recording of Documents; and (xii) if the lien is against an owner-occupied residence, as defined in Section 38-11-102, a statement meeting the requirements that the division has established by rule, describing the steps the owner of the owner-occupied residence may take to require a claimant to remove the lien as provided in Section 38-11-107. (b) (i) A claimant who is an original contractor or a supervising subcontractor may include in a notice of preconstruction lien the name, address, and telephone number of each subcontractor who is under contract with the claimant to provide preconstruction service that the claimant is under contract to provide. (ii) The inclusion of a subcontractor in a notice of preconstruction lien filed by another claimant is not a substitute for the subcontractor's own submission of a notice of preconstruction lien.

(a) A notice of preconstruction service lien shall include: (i) the claimant's name, mailing address, and telephone number; (ii) a statement that the claimant claims a preconstruction lien; (iii) the date the claimant's notice of preconstruction service was filed; (iv) the name of the person that employed the claimant; (v) a general description of the preconstruction service provided by the claimant; (vi) the date that the claimant last provided preconstruction service; (vii) the name, if known, of the reputed owner or, if not known, the name of the record owner; (viii) a description of the project property sufficient for identification; (ix) the principal amount, excluding interest, costs, and attorney fees, claimed by the claimant; (x) the claimant's signature or the signature of the claimant's authorized agent; (xi) an acknowledgment or certificate as required under Title 57, Chapter 3, Recording of Documents; and (xii) if the lien is against an owner-occupied residence, as defined in Section 38-11-102, a statement meeting the requirements that the division has established by rule, describing the steps the owner of the owner-occupied residence may take to require a claimant to remove the lien as provided in Section 38-11-107.

(i) the claimant's name, mailing address, and telephone number;

(ii) a statement that the claimant claims a preconstruction lien;

(iii) the date the claimant's notice of preconstruction service was filed;

(iv) the name of the person that employed the claimant;

(v) a general description of the preconstruction service provided by the claimant;

(vi) the date that the claimant last provided preconstruction service;

(vii) the name, if known, of the reputed owner or, if not known, the name of the record owner;

(viii) a description of the project property sufficient for identification;

(ix) the principal amount, excluding interest, costs, and attorney fees, claimed by the claimant;

(x) the claimant's signature or the signature of the claimant's authorized agent;

(xi) an acknowledgment or certificate as required under Title 57, Chapter 3, Recording of Documents; and

(xii) if the lien is against an owner-occupied residence, as defined in Section 38-11-102, a statement meeting the requirements that the division has established by rule, describing the steps the owner of the owner-occupied residence may take to require a claimant to remove the lien as provided in Section 38-11-107.

(b) (i) A claimant who is an original contractor or a supervising subcontractor may include in a notice of preconstruction lien the name, address, and telephone number of each subcontractor who is under contract with the claimant to provide preconstruction service that the claimant is under contract to provide. (ii) The inclusion of a subcontractor in a notice of preconstruction lien filed by another claimant is not a substitute for the subcontractor's own submission of a notice of preconstruction lien.

(i) A claimant who is an original contractor or a supervising subcontractor may include in a notice of preconstruction lien the name, address, and telephone number of each subcontractor who is under contract with the claimant to provide preconstruction service that the claimant is under contract to provide.

(ii) The inclusion of a subcontractor in a notice of preconstruction lien filed by another claimant is not a substitute for the subcontractor's own submission of a notice of preconstruction lien.

(4) (a) A county recorder: (i) shall record each notice of preconstruction lien in an index maintained for that purpose; and (ii) need not verify that a valid notice of preconstruction service is filed with respect to the claimed preconstruction lien. (b) All persons are considered to have notice of a notice of preconstruction lien from the time it is recorded.

(a) A county recorder: (i) shall record each notice of preconstruction lien in an index maintained for that purpose; and (ii) need not verify that a valid notice of preconstruction service is filed with respect to the claimed preconstruction lien.

(i) shall record each notice of preconstruction lien in an index maintained for that purpose; and

(ii) need not verify that a valid notice of preconstruction service is filed with respect to the claimed preconstruction lien.

(b) All persons are considered to have notice of a notice of preconstruction lien from the time it is recorded.

(5) (a) Within 30 days after a claimant's notice of preconstruction lien is recorded, the claimant shall send by certified mail a copy of the notice to the reputed or record owner. (b) If the record owner's address is not readily available to the claimant, the claimant may mail a copy of the notice to the owner's last-known address as it appears on the last completed assessment roll of the county in which the property is located. (c) A claimant's failure to mail a copy of the notice as required in this Subsection (5) precludes the claimant from being awarded costs and attorney fees against the reputed or record owner in an action to enforce the lien.

(a) Within 30 days after a claimant's notice of preconstruction lien is recorded, the claimant shall send by certified mail a copy of the notice to the reputed or record owner.

(b) If the record owner's address is not readily available to the claimant, the claimant may mail a copy of the notice to the owner's last-known address as it appears on the last completed assessment roll of the county in which the property is located.

(c) A claimant's failure to mail a copy of the notice as required in this Subsection (5) precludes the claimant from being awarded costs and attorney fees against the reputed or record owner in an action to enforce the lien.

(6) Nothing in this section may be construed to prohibit a claimant from recording a notice of preconstruction lien before completing the preconstruction service the claimant contracted to provide.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 402 - Notice of preconstruction lien -- Requirements.