(1) (a) (i) An applicant who has submitted a complete land use application, including the payment of all application fees, is entitled to substantive review of the application under the land use regulations: (A) in effect on the date that the application is complete; and (B) applicable to the application or to the information shown on the submitted application. (ii) An applicant is entitled to approval of a land use application if the application conforms to the requirements of the applicable land use regulations, land use decisions, and development standards in effect when the applicant submits a complete application and pays all application fees, unless: (A) the land use authority, on the record, formally finds that a compelling, countervailing public interest would be jeopardized by approving the application and specifies the compelling, countervailing public interest in writing; or (B) in the manner provided by local ordinance and before the applicant submits the application, the county formally initiates proceedings to amend the county's land use regulations in a manner that would prohibit approval of the application as submitted. (b) The county shall process an application without regard to proceedings the county initiated to amend the county's ordinances as described in Subsection (1)(a)(ii)(B) if: (i) 180 days have passed since the county initiated the proceedings; and (ii) the proceedings have not resulted in an enactment that prohibits approval of the application as submitted. (c) A land use application is considered submitted and complete when the applicant provides the application in a form that complies with the requirements of applicable ordinances and pays all applicable fees. (d) The continuing validity of an approval of a land use application is conditioned upon the applicant proceeding after approval to implement the approval with reasonable diligence. (e) A county may not impose on an applicant who has submitted a complete application a requirement that is not expressed: (i) in this chapter; (ii) in a county ordinance; or (iii) in a county specification for public improvements applicable to a subdivision or development that is in effect on the date that the applicant submits an application. (f) A county may not impose on a holder of an issued land use permit or a final, unexpired subdivision plat a requirement that is not expressed: (i) in a land use permit; (ii) on the subdivision plat; (iii) in a document on which the land use permit or subdivision plat is based; (iv) in the written record evidencing approval of the land use permit or subdivision plat; (v) in this chapter; or (vi) in a county ordinance. (g) Except as provided in Subsection (1)(h), a county may not withhold issuance of a certificate of occupancy or acceptance of subdivision improvements because of an applicant's failure to comply with a requirement that is not expressed: (i) in the building permit or subdivision plat, documents on which the building permit or subdivision plat is based, or the written record evidencing approval of the building permit or subdivision plat; or (ii) in this chapter or the county's ordinances. (h) A county may not unreasonably withhold issuance of a certificate of occupancy where an applicant has met all requirements essential for the public health, public safety, and general welfare of the occupants, in accordance with this chapter, unless: (i) the applicant and the county have agreed in a written document to the withholding of a certificate of occupancy; or (ii) the applicant has not provided a financial assurance for required and uncompleted landscaping or infrastructure improvements in accordance with an applicable ordinance that the legislative body adopts under this chapter.

(a) (i) An applicant who has submitted a complete land use application, including the payment of all application fees, is entitled to substantive review of the application under the land use regulations: (A) in effect on the date that the application is complete; and (B) applicable to the application or to the information shown on the submitted application. (ii) An applicant is entitled to approval of a land use application if the application conforms to the requirements of the applicable land use regulations, land use decisions, and development standards in effect when the applicant submits a complete application and pays all application fees, unless: (A) the land use authority, on the record, formally finds that a compelling, countervailing public interest would be jeopardized by approving the application and specifies the compelling, countervailing public interest in writing; or (B) in the manner provided by local ordinance and before the applicant submits the application, the county formally initiates proceedings to amend the county's land use regulations in a manner that would prohibit approval of the application as submitted.

(i) An applicant who has submitted a complete land use application, including the payment of all application fees, is entitled to substantive review of the application under the land use regulations: (A) in effect on the date that the application is complete; and (B) applicable to the application or to the information shown on the submitted application.

(A) in effect on the date that the application is complete; and

(B) applicable to the application or to the information shown on the submitted application.

(ii) An applicant is entitled to approval of a land use application if the application conforms to the requirements of the applicable land use regulations, land use decisions, and development standards in effect when the applicant submits a complete application and pays all application fees, unless: (A) the land use authority, on the record, formally finds that a compelling, countervailing public interest would be jeopardized by approving the application and specifies the compelling, countervailing public interest in writing; or (B) in the manner provided by local ordinance and before the applicant submits the application, the county formally initiates proceedings to amend the county's land use regulations in a manner that would prohibit approval of the application as submitted.

(A) the land use authority, on the record, formally finds that a compelling, countervailing public interest would be jeopardized by approving the application and specifies the compelling, countervailing public interest in writing; or

(B) in the manner provided by local ordinance and before the applicant submits the application, the county formally initiates proceedings to amend the county's land use regulations in a manner that would prohibit approval of the application as submitted.

(b) The county shall process an application without regard to proceedings the county initiated to amend the county's ordinances as described in Subsection (1)(a)(ii)(B) if: (i) 180 days have passed since the county initiated the proceedings; and (ii) the proceedings have not resulted in an enactment that prohibits approval of the application as submitted.

(i) 180 days have passed since the county initiated the proceedings; and

(ii) the proceedings have not resulted in an enactment that prohibits approval of the application as submitted.

(c) A land use application is considered submitted and complete when the applicant provides the application in a form that complies with the requirements of applicable ordinances and pays all applicable fees.

(d) The continuing validity of an approval of a land use application is conditioned upon the applicant proceeding after approval to implement the approval with reasonable diligence.

(e) A county may not impose on an applicant who has submitted a complete application a requirement that is not expressed: (i) in this chapter; (ii) in a county ordinance; or (iii) in a county specification for public improvements applicable to a subdivision or development that is in effect on the date that the applicant submits an application.

(i) in this chapter;

(ii) in a county ordinance; or

(iii) in a county specification for public improvements applicable to a subdivision or development that is in effect on the date that the applicant submits an application.

(f) A county may not impose on a holder of an issued land use permit or a final, unexpired subdivision plat a requirement that is not expressed: (i) in a land use permit; (ii) on the subdivision plat; (iii) in a document on which the land use permit or subdivision plat is based; (iv) in the written record evidencing approval of the land use permit or subdivision plat; (v) in this chapter; or (vi) in a county ordinance.

(i) in a land use permit;

(ii) on the subdivision plat;

(iii) in a document on which the land use permit or subdivision plat is based;

(iv) in the written record evidencing approval of the land use permit or subdivision plat;

(v) in this chapter; or

(vi) in a county ordinance.

(g) Except as provided in Subsection (1)(h), a county may not withhold issuance of a certificate of occupancy or acceptance of subdivision improvements because of an applicant's failure to comply with a requirement that is not expressed: (i) in the building permit or subdivision plat, documents on which the building permit or subdivision plat is based, or the written record evidencing approval of the building permit or subdivision plat; or (ii) in this chapter or the county's ordinances.

(i) in the building permit or subdivision plat, documents on which the building permit or subdivision plat is based, or the written record evidencing approval of the building permit or subdivision plat; or

(ii) in this chapter or the county's ordinances.

(h) A county may not unreasonably withhold issuance of a certificate of occupancy where an applicant has met all requirements essential for the public health, public safety, and general welfare of the occupants, in accordance with this chapter, unless: (i) the applicant and the county have agreed in a written document to the withholding of a certificate of occupancy; or (ii) the applicant has not provided a financial assurance for required and uncompleted landscaping or infrastructure improvements in accordance with an applicable ordinance that the legislative body adopts under this chapter.

(i) the applicant and the county have agreed in a written document to the withholding of a certificate of occupancy; or

(ii) the applicant has not provided a financial assurance for required and uncompleted landscaping or infrastructure improvements in accordance with an applicable ordinance that the legislative body adopts under this chapter.

(2) A county is bound by the terms and standards of applicable land use regulations and shall comply with mandatory provisions of those regulations.

(3) A county may not, as a condition of land use application approval, require a person filing a land use application to obtain documentation regarding a school district's willingness, capacity, or ability to serve the development proposed in the land use application.

(4) Upon a specified public agency's submission of a development plan and schedule as required in Subsection 17-27a-305(8) that complies with the requirements of that subsection, the specified public agency vests in the county's applicable land use maps, zoning map, hookup fees, impact fees, other applicable development fees, and land use regulations in effect on the date of submission.

(5) (a) If sponsors of a referendum timely challenge a project in accordance with Subsection 20A-7-601(5)(a), the project's affected owner may rescind the project's land use approval by delivering a written notice: (i) to the local clerk as defined in Section 20A-7-101; and (ii) no later than seven days after the day on which a petition for a referendum is determined sufficient under Section 20A-7-607(5). (b) Upon delivery of a written notice described in Subsection (5)(a) the following are rescinded and are of no further force or effect: (i) the relevant land use approval; and (ii) any land use regulation enacted specifically in relation to the land use approval.

(a) If sponsors of a referendum timely challenge a project in accordance with Subsection 20A-7-601(5)(a), the project's affected owner may rescind the project's land use approval by delivering a written notice: (i) to the local clerk as defined in Section 20A-7-101; and (ii) no later than seven days after the day on which a petition for a referendum is determined sufficient under Section 20A-7-607(5).

(i) to the local clerk as defined in Section 20A-7-101; and

(ii) no later than seven days after the day on which a petition for a referendum is determined sufficient under Section 20A-7-607(5).

(b) Upon delivery of a written notice described in Subsection (5)(a) the following are rescinded and are of no further force or effect: (i) the relevant land use approval; and (ii) any land use regulation enacted specifically in relation to the land use approval.

(i) the relevant land use approval; and

(ii) any land use regulation enacted specifically in relation to the land use approval.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 508 - Applicant's entitlement to land use application approval -- Application relating to land in a high priority transportation corridor -- County's requirements and limitations -- Vesting upon submission of development plan and schedule.