LegalFix

§ 13-18-103. Applications for designation as major energy project, joint review, and expedited review -- Revocation or termination -- Judicial review.

TN Code § 13-18-103 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(a)

(1) Any person planning or proposing an energy project may apply to the contact agency for an order designating such project as a priority energy project. An application shall include such detailed information concerning the project as the contact agency may require by rule to enable the contact agency to make a designation, including a detailed design proposal for the project, detailed economic data on the costs of the project, and an analysis of environmental impacts of the project; provided, that the adequacy of an application under this section shall not be subject to judicial review.

(2) Not later than five (5) days after the receipt of a designation request, the contact agency shall publish notice of the filing of the designation request, together with a brief description thereof in newspapers of general circulation in the area of the project and in Nashville. The contact agency shall also keep on file and make available for public inspection and copying at the main office of the contact agency and in such other places as the contact agency deems appropriate such portions of the full designation request.

(3) No project shall be designated a major energy project unless the contact agency finds that the project is likely to reduce directly or indirectly the state's dependence on imported energy and meets the capital expenditure requirements set out in § 13-18-102(11).

(b)

(1) Any person who plans to develop an energy project may request the contact agency to designate the project a major energy project and to approve the project for joint review. The chief executive officer of the contact agency shall determine whether the proposed project is a major energy project and whether it qualifies for the joint review process. The chief executive officer of the contact agency shall consult with agencies who will be involved in issuing permits and with any other agency to determine whether the proposed project should be so designated. If the chief executive officer decides the project should be so designated, the chief executive officer shall recommend the designation to the governor for the governor's concurrence.

(2) If the governor approves designation of the proposed project as a major energy project, the governor shall issue an executive order designating a lead state agency, approving the project for the joint review process, and providing for a joint review staff.

(3) An applicant may request the joint review process for parts of the regulatory as well as for the entire process.

(c)

(1) In the alternative, any person who plans to develop an energy project may request the contact agency to designate the project a major energy project and to approve the project for expedited review. In the case of a request for expedited review, the applicant shall indicate which agencies or parts of the regulatory process the applicant wishes to have considered under the terms of this chapter. Expedited review shall enjoy the expedited judicial hearings provided for by this chapter. In the case of a request for expedited review, the chief executive officer shall make the determinations provided for in subsections (a) and (b) and submit such chief executive officer's recommendation to the governor. If the governor approves, the governor has to issue an executive order specifying the agencies or parts of the regulatory process to be included in expedited review and the procedure to be followed.

(2) An applicant may seek to be declared a major energy project and to utilize expedited review solely to enjoy any one (1) of the benefits set out in this chapter, such as expedited judicial review or consolidation of hearings, but such applicant shall be limited to the relief sought.

(d) A request for designation of a project as a major energy project and use of the joint review process, or for expedited review, shall be approved or rejected within one (1) month of the initial request.

(e) Once an energy project has been designated a major energy project, and the joint review process or expedited review process has begun, the designation and process shall not be revoked or terminated unless requested by the applicant or unless procured by fraud or misrepresentation.

(f) A decision of the contact agency or governor designating an energy project as a major energy project shall not be subject to judicial review, except for fraud or misrepresentation and no court shall hold unlawful or set aside any department or agency action, finding, rule, or conclusion on the basis of a decision designating an energy project as a major energy project.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
§ 13-18-103. Applications for designation as major energy project, joint review, and expedited review -- Revocation or termination -- Judicial review.