LegalFix

Section 44-56-60. Annual evaluation; permit requirements; disposal limits; preference for in-state generated waste.

SC Code § 44-56-60 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(a)(1) In order to provide the General Assembly with the information it needs to accomplish the above goals, the Department of Health and Environmental Control shall evaluate annually the effects of new and existing waste management technologies, alternate methods of storage or disposal, recycling, incineration, waste minimization laws and practices, and other factors that tend to reduce the volume of hazardous waste. The results of the department's evaluation must be reported to the General Assembly not later than February first of each year, beginning in 1991, in a form that will permit the General Assembly to determine whether or not hazardous waste landfill capacity in this State should be reduced.

(2) No person may construct, substantially alter, or operate a hazardous waste treatment, storage, or disposal facility or site, nor may a person transport, store, treat, or dispose of hazardous waste without first obtaining a permit from the department for the facility, site, or activity. Beginning July 1, 1990, permitted hazardous waste disposal sites are restricted to a rate of land disposal by burial not to exceed one hundred twenty thousand tons of hazardous waste for the twelve-month period ending July 1, 1991. On July 1, 1991, permitted hazardous waste disposal sites are restricted to a rate of land disposal by burial not to exceed one hundred ten thousand tons of hazardous waste for each twelve-month period thereafter within the permitted area of the site.

(3) During a twelve-month period, the commissioner may allow land disposal by burial in excess of the limitation upon certification of the department that:

(A) disposal by land burial from a particular site in South Carolina is necessary to protect the health and safety of the people of this State; or

(B) at least one hundred ten thousand tons of hazardous waste disposed of by land burial in this State during the twelve-month period was generated in South Carolina.

During each twelve-month period, a person operating a hazardous waste disposal facility or site shall reserve at least the same capacity to dispose of hazardous waste generated in South Carolina that was disposed of by burial at that facility or site during the previous year excluding capacity that was used to dispose of hazardous waste pursuant to subitem (A). No more hazardous waste from out of state shall be buried in South Carolina than was buried in the previous twelve-month period.

Certification must be issued to the party seeking to use land disposal of the waste, and the certification must be presented to the operator of the facility at the time of disposal. The facility shall submit this certification with its regular report to the department of permitted activity at the disposal site.

(b) Any person who:

1. Owns or operates a facility required to have a permit under this section which facility is in existence on the effective date of this section;

2. Has complied with the requirements of Section 44-56-120; and

3. Has made an application for a permit under this section is deemed to have been issued the permit until such time as final administrative disposition of each application is made by the department, unless final administrative disposition of each application has not been made because of the failure of the applicant to furnish information reasonably required or requested in order to process the application.

(c) Before issuance of a permit, the Department shall require:

1. Evidence of liability coverage for sudden and nonsudden accidental occurrences in an amount the Department may determine necessary for the protection of the public health and safety, and the environment;

2. Evidence of financial assurance in the form and amount as the Department may determine to be necessary to ensure that, upon abandonment, cessation, or interruption of the operation of a facility or site, all appropriate measures are taken to prevent present and future damage to the public health and safety and to the environment. The Department shall assume continuing responsibility for environmental monitoring and for any response actions necessary to ensure the health and safety of the state's citizens for any hazardous waste disposal or treatment sites permitted under this chapter when the facilities, sites, or activities close and all responsibilities required of any other party by any state or federal law or regulation cease. The Department's responsibility for monitoring and response action is neither a limitation nor a termination of the liability of generators, transporters, or the operators of the facility under any provision of law or at common law.

3. Evidence of other financial assurance in such forms and amounts as the department determines to be necessary to ensure the adequate availability of funds for clean-up costs and restoration of environmental impairment arising from the facility.

HISTORY: 1978 Act No. 436 Section 4; 1983 Act No. 151 Part II Section 31C; 1984 Act No. 397, Section 4; 1985 Act No. 140, Section 5; 1989 Act No. 196, Section 6; 1990 Act No. 590, Section 2.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 44-56-60. Annual evaluation; permit requirements; disposal limits; preference for in-state generated waste.