Section 537.630 - Time allowed for construction work under permit; extension; certificate of completion; survey; ground water right certificate; requirements for supplemental water right.

OR Rev Stat § 537.630 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(a) June 29, 2005;

(b) The time specified in the permit to perfect the water right; or

(c) The time specified in the last-approved extension of time to perfect the water right.

(2) Except for the holder of a permit for municipal use, the holder of a permit issued pursuant to ORS 537.625 shall prosecute the construction of a well or other means of developing and securing the ground water with reasonable diligence and complete the construction within a reasonable time fixed in the permit by the Water Resources Department, not to exceed five years after the date of approval of the application. However, the department, for good cause shown, shall order and allow an extension of time, including an extension beyond the five-year period, for the completion of the well or other means of developing and securing the ground water or for complete application of water to beneficial use. In determining the extension, the department shall give due weight to the considerations described under ORS 539.010 (5) and to whether other governmental requirements relating to the project have significantly delayed completion of construction or perfection of the right.

(3) The holder of a permit for municipal use shall commence and complete the construction of any proposed works within 20 years from the date on which the permit for municipal use is issued under ORS 537.625. The construction must proceed with reasonable diligence and be completed within the time specified in the permit, not to exceed 20 years. However, the department may order and allow an extension of time to complete construction or to perfect a water right beyond the time specified in the permit under the following conditions:

(a) The holder shows good cause. In determining the extension, the department shall give due weight to the considerations described under ORS 539.010 (5) and to whether other governmental requirements relating to the project have significantly delayed completion of construction or perfection of the right;

(b) The extension of time is conditioned to require that the holder submit and obtain department approval of a water management and conservation plan;

(c) The extension of time is conditioned to provide that the holder may appropriate the undeveloped portion of the permit only upon approval by the department of a water management and conservation plan; and

(d) For the first extension issued after June 29, 2005, for a permit for municipal use issued before November 2, 1998, the department finds that the undeveloped portion of the permit is conditioned to maintain, in the portions of waterways affected by water use under the permit, the persistence of fish species listed as sensitive, threatened or endangered under state or federal law. The department shall base its finding on existing data and upon the advice of the State Department of Fish and Wildlife. An existing fish protection agreement between the permit holder and a state or federal agency that includes conditions to maintain the persistence of any listed fish species in the affected portion of the waterway is conclusive for purposes of the finding.

(4) If the construction of any well or other means of developing and securing the ground water is completed after the date of approval of the application for a permit under ORS 537.625, within 30 days after the completion, or if the construction is completed before the date of approval, within 30 days after the date of approval, the permit holder shall file a certificate of completion with the Water Resources Department, disclosing:

(a) The depth to the water table;

(b) The depth, diameter and type of each well, and the kind and amount of the casing;

(c) The capacity of the well pump in gallons per minute and the drawdown thereof;

(d) The identity of the record owner of any property that was described in the application for a permit under ORS 537.625 but is not included in the certificate of completion; and

(e) Any other information the department considers necessary.

(5) Upon completion of beneficial use necessary to secure the ground water as required under this section, the permit holder shall hire a water right examiner certified under ORS 537.798 to survey the appropriation. Within one year after applying the water to beneficial use or the beneficial use date allowed in the permit, the permit holder shall submit the survey as required by the Water Resources Department to the department along with the certificate of completion required under subsection (4) of this section. If any property described in the permit is not included in the request for a water right certificate, the holder of the permit shall state the identity of the record owner of that property.

(6) After the department has received a certificate of completion and a copy of the survey as required by subsections (4) and (5) of this section that show, to the satisfaction of the department, that an appropriation has been perfected in accordance with the provisions of ORS 537.505 to 537.795 and 537.992, except as provided in subsection (7) of this section, the department shall issue a ground water right certificate of the same character as that described in ORS 537.700. The certificate shall be recorded and transmitted to the applicant as provided in ORS 537.700.

(7) The department may not issue a water right certificate for municipal use under this section if:

(a) An extension of time is required; and

(b) The order approving the extension of time has not become final by operation of law or on appeal.

(8) The procedure for cancellation of a permit shall be as provided in ORS 537.260.

(9) Notwithstanding ORS 537.410, for purposes of obtaining a water right certificate under subsection (6) of this section for a supplemental water right, the holder of a permit shall have a facility capable of handling the full rate and duty of water requested from the supplemental source and be otherwise ready, willing and able to use the amount of water requested, up to the amount of water approved in the water right permit. To obtain a certificate for a supplemental water right, the holder is not required to have actually used water from the supplemental source if:

(a) Water was available from the source of the primary water right and the primary water right was used pursuant to the terms of the primary water right; or

(b) The nonuse of water from the supplemental source occurred during a period of time within which the exercise of the supplemental water right permit was not necessary due to climatic conditions. [1955 c.708 §12; 1959 c.437 §5; 1985 c.617 §2; 1985 c.673 §202; 1987 c.542 §8; 1995 c.367 §3; 1995 c.416 §34; 1997 c.446 §8; 1999 c.453 §2; 2005 c.410 §2; 2017 c.704 §4]

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 537.630 - Time allowed for construction work under permit; extension; certificate of completion; survey; ground water right certificate; requirements for supplemental water right.