Section 468B.045 - Certification of change to hydroelectric power project; notification of federal agency.

OR Rev Stat § 468B.045 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1) The director shall:

(a) Solicit and consider the comments of all affected state agencies relative to adverse impacts on water quality caused by changes in the project, according to sections 301, 302, 303, 306 and 307 of the Federal Water Pollution Control Act, P.L. 92-500, as amended.

(b) Approve or deny a certification of the proposed change after making findings that the approval or denial is consistent with:

(A) Rules adopted by the Environmental Quality Commission on water quality;

(B) Provisions of sections 301, 302, 303, 306 and 307 of the Federal Water Pollution Control Act, P.L. 92-500, as amended;

(C) Except as provided in subsection (2) of this section, standards established in ORS 543.017 and rules adopted by the Water Resources Commission implementing such standards; and

(D) Except as provided in subsection (2) of this section, standards of other state and local agencies that are consistent with the standards of ORS 543.017 and that the director determines are other appropriate requirements of state law according to section 401 of the Federal Water Pollution Control Act, P.L. 92-500, as amended.

(2) If the proposed certification is for a change to a federally licensed project, as defined in ORS 543A.005, that has been reauthorized under ORS 543A.060 to 543A.300, or for a change to a project that is subject to federal relicensing but that operates under a water right that does not expire, the director shall not determine consistency under subsection (1)(b)(C) and (D) of this section, but shall determine consistency with the rules and provisions referred to in subsection (1)(b)(A) and (B) of this section, standards established in ORS 543A.025 (2) to (4), rules adopted by the Water Resources Commission implementing such standards and rules of other state and local agencies that are consistent with the standards of ORS 543A.025 (2) to (4) and that the director determines are other appropriate requirements of state law according to section 401 of the Federal Water Pollution Control Act, P.L. 92-500, as amended.

(3) On the basis of the evaluation and determination under subsections (1) and (2) of this section, the director shall notify the appropriate federal agency that:

(a) The proposed change to the project is approved; or

(b) There is no longer reasonable assurance that the project as changed complies with the applicable provisions of the Federal Water Pollution Control Act, P.L. 92-500, as amended, because of changes in the proposed project since the director issued the construction license or permit certification. [Formerly 468.734; 1993 c.544 §2; 1997 c.449 §40a]

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 468B.045 - Certification of change to hydroelectric power project; notification of federal agency.