Section 455.467 - Timelines for approval or disapproval of certain specialty code building plans; exceptions; phased permit systems; failure to adhere to timelines.

OR Rev Stat § 455.467 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(a) For a jurisdiction with a population that is less than 300,000, within 10 business days of receiving a complete application, or shall implement the process described in ORS 455.465.

(b) For a jurisdiction with a population that is 300,000 or more, within 15 business days of receiving a complete application, or shall implement the process described in ORS 455.465.

(2) The 10-day and 15-day requirements in subsection (1) of this section do not apply if:

(a) The plan requires approval by federal, state or local agencies outside the jurisdiction of the issuing agency;

(b) The plan is for a complex structure that requires additional review as determined by the department or municipality; or

(c) Based on conditions that exist in the affected municipality, the Director of the Department of Consumer and Business Services authorizes a different plan review schedule as described in a building inspection program submitted under ORS 455.148 or 455.150.

(3) For specialty code plan reviews of commercial structures, a municipality shall include in its building inspection program submitted under ORS 455.148 or 455.150 a process for plan review services. The municipality shall include in its program detailed reasons supporting the proposed plan review process. The plan review services provided by the municipality shall:

(a) Allow an applicant to defer the submittal of plans for one or more construction phases for a commercial construction project in accordance with the state building code; and

(b) Allow an applicant to receive permits for each of the phases of a commercial construction project as described in the state building code when the plan review for that phase is approved.

(4) For a phased commercial construction project as described in subsection (3) of this section, the municipality shall inform the applicant of the detailed plans necessary for each phase of the project and the estimated time for initial and phased review of the building plans for conformance with the state building code.

(5) An applicant submitting plans under subsection (3) of this section is responsible for ensuring that the project meets all specialty code requirements and that the project does not proceed beyond the level of approval authorized by the building official.

(6) A municipality that repeatedly fails to meet the plan review period described in this section or otherwise authorized in its building inspection program submitted under ORS 455.148 or 455.150 shall be considered to be engaging in a pattern of conduct of failing to provide timely plan reviews under ORS 455.160. [1999 c.1045 §21; 2001 c.384 §1; 2001 c.573 §13; 2003 c.675 §28]

Note: See note under 455.455.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 455.467 - Timelines for approval or disapproval of certain specialty code building plans; exceptions; phased permit systems; failure to adhere to timelines.