LegalFix

§ 62-133.15 - (Expires July 1, 2021 see note) Cost recovery for natural gas economic development infrastructure.

NC Gen Stat § 62-133.15 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

62-133.15. (Expires July 1, 2021 - see note) Cost recovery for natural gas economic development infrastructure.

(a) Purpose. - The purpose of this section is to prescribe a methodology for cost recovery by a natural gas local distribution company that constructs natural gas economic development infrastructure to serve a project the Department of Commerce determines is an eligible project under G.S. 143B-437.021. The Commission shall adopt rules to implement this section.

(b) Eligibility. - Cost recovery under this section is limited to natural gas economic development infrastructure the Commission determines satisfies all of the following conditions:

(1) The project will be located in an area where adequate natural gas infrastructure for the eligible project is not economically feasible.

(2) Either the developer, prospective customer, or the occupant of the eligible project provides, prior to initiation of construction of the natural gas economic development infrastructure, a binding commitment in the form of a commercial contract or other form acceptable to the Commission to the natural gas local distribution company regarding service needed for a period of at least 10 years from the date the gas is made available.

(3) The projected margin revenues not recoverable under G.S. 62-133.4 from the eligible project will not be sufficient to cover the cost of the natural gas infrastructure associated with the project.

(c) Economic Feasibility. - The Commission shall permit a natural gas local distribution company to recover reasonable and prudent natural gas economic development infrastructure costs only to the extent necessary to make the construction of the infrastructure economically feasible, as determined by the Commission. In determining economic feasibility, the Commission shall employ the net present value method of analysis. Only natural gas economic development infrastructure with a negative net present value shall be determined to be economically infeasible.

(d) Costs Recoverable. - Eligible economic development infrastructure development costs are the reasonable and prudent costs determined by the Commission to be both directly related to the construction of natural gas infrastructure for an eligible project and economically infeasible. The costs may include any of the following:

(1) Planning costs.

(2) Development costs.

(3) Construction costs and an allowance for funds used during construction and a return on investment once the project is completed, calculated using the pretax overall rate of return approved by the Commission in the company's most recent general rate case.

(4) A revenue retention factor.

(5) Depreciation.

(6) Property taxes.

(e) Rate Adjustment Surcharge Mechanism. - The Commission shall permit recovery of eligible economic development infrastructure costs in a rate adjustment surcharge mechanism. The mechanism shall allow for recovery on an annual or semiannual basis, as determined by the Commission, subject to audit and reconciliation procedures. Any rate adjustment surcharge mechanism adopted under this section shall terminate upon the earlier of the full recovery of the costs allowed under subsection (d) of this section or the natural gas local distribution company's next general rate case in which the eligible infrastructure development costs shall be included in the natural gas distribution company's rate base. Nothing in this section precludes the natural gas local distribution company from recovering eligible economic development infrastructure costs in a general rate case.

(f) Limitations. - A natural gas local distribution company shall not invest more than twenty-five million dollars ($25,000,000) of eligible infrastructure development costs in any year. The aggregate amount of eligible infrastructure development costs recovered under rate adjustment surcharge mechanisms for all natural gas local distribution companies in the State cannot exceed seventy-five million dollars ($75,000,000). Cumulative rate adjustments allowed under a rate adjustment surcharge mechanism approved by the Commission under this section shall not exceed five percent (5%) of the total annual service margin revenues not recoverable under G.S. 62-133.4 approved by the Commission in the natural gas local distribution company's last general rate case.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
§ 62-133.15 - (Expires July 1, 2021 see note) Cost recovery for natural gas economic development infrastructure.