(a) the basis of the need for the facility;

(b) the nature of the probable environmental impact;

(c) that the facility represents the minimum adverse environmental impact, considering the state of available technology and the nature and economics of the various alternatives, and other pertinent considerations including but not limited to, the effect on agricultural lands, wetlands, parklands and river corridors traversed;

(d) that the facility represents a minimum adverse impact on active farming operations that produce crops, livestock and livestock products, as defined in section three hundred one of the agriculture and markets law, considering the state of available technology and the nature and economics of various alternatives, and the ownership and easement rights of the impacted property;

(e) in the case of an electric transmission line, (1) what part, if any, of the line shall be located underground; (2) that such facility conforms to a long-range plan for expansion of the electric power grid of the electric systems serving this state and interconnected utility systems, which will serve the interests of electric system economy and reliability;

(f) in the case of a gas transmission line, that the location of the line will not pose an undue hazard to persons or property along the area traversed by the line;

(g) that the location of the facility as proposed conforms to applicable state and local laws and regulations issued thereunder, all of which shall be binding upon the commission, except that the commission may refuse to apply any local ordinance, law, resolution or other action or any regulation issued thereunder or any local standard or requirement which would be otherwise applicable if it finds that as applied to the proposed facility such is unreasonably restrictive in view of the existing technology, or of factors of cost or economics, or of the needs of consumers whether located inside or outside of such municipality;

(h) that the facility will serve the public interest, convenience, and necessity, provided, however, that a determination of necessity made by the power authority of the state of New York pursuant to section ten hundred five of the public authorities law for a major utility transmission facility for which an application has been filed prior to July first, nineteen hundred seventy-eight pursuant to section one hundred twenty-two of this chapter, shall be conclusive on the commission. 2. In the case of an electric transmission line to be constructed by the power authority of the state of New York and located in part under the waters of Long Island Sound and for the remaining part underground, the commission shall make only the findings and determinations required by paragraphs (b), (c) and (f) of subdivision one of this section and, on the basis of such findings and determinations, shall grant, grant in part, or deny the certificate. 3. If the commission determines that the location of all or a part of the proposed facility should be modified, it may condition its certificate upon such modification, provided that the municipalities and persons residing in such municipalities affected by the modification shall have had notice of the application as provided in subdivision two of section one hundred twenty-two. 4. A copy of the order and any opinion issued therewith pursuant to section one hundred twenty-seven shall be served upon each party.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
126 - The Decision.