52:32-41. Construction contracts, timely payment to subs and suppliers, procedure

2. a. Prior to the issuance of a progress payment by a State agency to a prime contractor, the prime contractor shall certify to the State agency that a subcontractor or supplier has been paid any amount due from any previous progress payment and shall be paid any amount due from the current progress payment, or that there exists a valid basis under the terms of the subcontractor's or supplier's contract to withhold payment from the subcontractor or supplier and therefore payment is withheld.

b. If the prime contractor withholds payment from a subcontractor or supplier, the prime contractor shall provide to the subcontractor or supplier written notice of a withholding of payment. The notice shall detail the reason for withholding payment and state the amount of payment withheld. A copy of the notice shall be provided to the bonding company providing the performance bond for the general contractor and to the State agency.

c. In addition to any amount due, a subcontractor or supplier shall also receive from a prime contractor interest on the amount due at a rate equal to the prime rate plus 1% if a subcontractor or supplier is not paid within 10 calendar days after receipt by the prime contractor of payment by a State agency for completed work which is the subject of a subcontract or a material supply agreement and if no valid basis exists for withholding payment. This interest shall begin to accrue on the 10th calendar day after receipt of payment by the prime contractor. In addition, a subcontractor or supplier shall receive any court costs incurred by the subcontractor or supplier to collect payments withheld without a valid basis by the prime contractor.

d. If court action is taken by a subcontractor or supplier to collect payments withheld by a prime contractor and it is determined that a valid basis existed for the withholding of those payments, the subcontractor or supplier shall be liable for any court costs incurred by the prime contractor in connection with the action.

L.1991,c.507,s.2.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 52:32-41 - Construction contracts, timely payment to subs and suppliers, procedure