57-1407. Commission; duties; public meetings; agency reports; approval by commission; considerations.

(1) After receipt of an application under section 57-1405, the commission shall:

(a) Within sixty days, schedule a public hearing;

(b) Notify the pipeline carrier of the time, place, and purpose of the public hearing;

(c) Publish a notice of the time, place, and purpose of the public hearing in at least one newspaper of general circulation in each county in which the major oil pipeline is to be constructed; and

(d) Serve notice of the public hearing upon the governing bodies of the counties and municipalities through which the proposed route of the major oil pipeline would be located as specified in subdivision (2)(d) of section 57-1405.

(2) The commission may hold additional public meetings for the purpose of receiving input from the public at locations as close as practicable to the proposed route of the major oil pipeline. The commission shall make the public input part of the record.

(3) If requested by the commission, the following agencies shall file a report with the commission, prior to the hearing on the application, regarding information within the respective agencies' area of expertise relating to the impact of the major oil pipeline on any area within the respective agencies' jurisdiction, including in such report opinions regarding the advisability of approving, denying, or modifying the location of the proposed route of the major oil pipeline: The Department of Environment and Energy, the Department of Natural Resources, the Department of Revenue, the Department of Transportation, the Game and Parks Commission, the Nebraska Oil and Gas Conservation Commission, the Nebraska State Historical Society, the State Fire Marshal, and the Board of Educational Lands and Funds. The agencies may submit a request for reimbursement of reasonable and necessary expenses incurred for any consultants hired pursuant to this subsection.

(4) An application under the Major Oil Pipeline Siting Act shall be approved if the proposed route of the major oil pipeline is determined by the Public Service Commission to be in the public interest. The pipeline carrier shall have the burden to establish that the proposed route of the major oil pipeline would serve the public interest. In determining whether the pipeline carrier has met its burden, the commission shall not evaluate safety considerations, including the risk or impact of spills or leaks from the major oil pipeline, but the commission shall evaluate:

(a) Whether the pipeline carrier has demonstrated compliance with all applicable state statutes, rules, and regulations and local ordinances;

(b) Evidence of the impact due to intrusion upon natural resources and not due to safety of the proposed route of the major oil pipeline to the natural resources of Nebraska, including evidence regarding the irreversible and irretrievable commitments of land areas and connected natural resources and the depletion of beneficial uses of the natural resources;

(c) Evidence of methods to minimize or mitigate the potential impacts of the major oil pipeline to natural resources;

(d) Evidence regarding the economic and social impacts of the major oil pipeline;

(e) Whether any other utility corridor exists that could feasibly and beneficially be used for the route of the major oil pipeline;

(f) The impact of the major oil pipeline on the orderly development of the area around the proposed route of the major oil pipeline;

(g) The reports of the agencies filed pursuant to subsection (3) of this section; and

(h) The views of the governing bodies of the counties and municipalities in the area around the proposed route of the major oil pipeline.

Source

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
57-1407 Commission; duties; public meetings; agency reports; approval by commission; considerations.