37-1725 Alternative technical concepts; evaluation of proposals; commission; power to negotiate.

NE Code § 37-1725 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

37-1725. Alternative technical concepts; evaluation of proposals; commission; power to negotiate.

(1) Design-builders shall submit proposals as required by the request for proposals. The commission may meet with individual design-builders prior to the time of submitting the proposal and may have discussions concerning alternative technical concepts. If an alternative technical concept provides a solution that is equal to or better than the requirements in the request for proposals and the alternative technical concept is acceptable to the commission, it may be incorporated as part of the proposal by the design-builder. Notwithstanding any other provision of state law to the contrary, alternative technical concepts shall be confidential and not disclosed to other design-builders or members of the public from the time the proposals are submitted until such proposals are opened by the commission.

(2) Proposals shall be sealed and shall not be opened until expiration of the time established for making the proposals as set forth in the request for proposals.

(3) Proposals may be withdrawn at any time prior to the opening of such proposals in which case no stipend shall be paid. The commission shall have the right to reject any and all proposals at no cost to the commission other than any stipend for design-builders who have submitted responsive proposals. The commission may thereafter solicit new proposals using the same or different project performance criteria or may cancel the design-build solicitation.

(4) The commission shall rank the design-builders in order of best value pursuant to the criteria in the request for proposals. The commission may meet with design-builders prior to ranking.

(5) The commission may attempt to negotiate a design-build contract with the highest ranked design-builder selected by the commission and may enter into a design-build contract after negotiations. If the commission is unable to negotiate a satisfactory design-build contract with the highest ranked design-builder, the commission may terminate negotiations with that design-builder. The commission may then undertake negotiations with the second highest ranked design-builder and may enter into a design-build contract after negotiations. If the commission is unable to negotiate a satisfactory contract with the second highest ranked design-builder, the commission may undertake negotiations with the third highest ranked design-builder, if any, and may enter into a design-build contract after negotiations.

(6) If the commission is unable to negotiate a satisfactory contract with any of the ranked design-builders, the commission may either revise the request for proposals and solicit new proposals or cancel the design-build process under the State Park System Construction Alternatives Act.

Source

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
37-1725 Alternative technical concepts; evaluation of proposals; commission; power to negotiate.