15-24-3005. Electrical generation facility impact fee for local governmental units and school districts -- wind generation facility impact fee

MT Code § 15-24-3005 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

15-24-3005. Electrical generation facility impact fee for local governmental units and school districts -- wind generation facility impact fee. (1) (a) If an owner or operator of an electrical generation facility, as defined in 15-24-3001, is exempt from property taxation pursuant to 15-24-3001, the owner or operator of the facility is subject to an initial local government and local school impact fee. In the first 2 years of construction, the impact fee may not exceed 0.75% of the total cost of constructing the electrical generation facility.

(b) In the case of a generation facility powered by oil or gas turbines, the impact fee may not exceed 0.1% of the total construction cost in the remaining 3 years of the tax exemption period as provided in 15-24-3001.

(c) In the case of any other generation facility, the impact fee may not exceed 0.1% of the total construction cost in the subsequent 4 years and may not exceed 0.08% of the total construction cost in the remaining 4 years of the tax exemption period as provided in 15-24-3001.

(2) Except as provided in subsection (4), the jurisdictional area of a local governmental unit in which an electrical generation facility or wind generation facility is located is the local governmental unit that is authorized to assess the impact fee pursuant to 15-24-3004(1) or subsection (1) of this section.

(3) The impact fee must be distributed to the local governmental unit for local impacts and to the impacted school districts.

(4) Subject to the conditions of 15-24-3006 and subsection (5) of this section, if the electrical generation facility or wind generation facility is located within the jurisdictional areas of multiple local governmental units of the county or contiguous counties, the local governmental units may enter into an interlocal agreement under Title 7, chapter 11, part 1, to determine how the fee should be distributed among the various local governmental units and impacted school districts pursuant to subsection (3). The county in which the electrical generation facility or wind generation facility is located is authorized to assess the fee under the interlocal agreement.

(5) For purposes of 15-24-3004 and this section, a "local governmental unit" means a county, city, or town. If an exempt electrical generation facility or wind generation facility is located within a tax increment financing district, the tax increment financing district is considered a local governmental unit and is entitled to the distribution of impact fees under this section. A tax increment financing district may not receive a distribution of impact fees if an exempt electrical generation facility or wind generation facility is not located within the district.

(6) Impact fees imposed under 15-24-3004(2)(b) or under subsection (4) of this section must be deposited in the county electrical energy generation impact fee reserve account established in 15-24-3006 for the county in which the electrical generation facility is located. Money in the account may not be expended until the multiple local governmental units have entered into an interlocal agreement.

History: En. Sec. 3, Ch. 592, L. 2001; amd. Sec. 16, Ch. 130, L. 2005; amd. Sec. 8, Ch. 563, L. 2005.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
15-24-3005. Electrical generation facility impact fee for local governmental units and school districts -- wind generation facility impact fee