LegalFix

Section 444.766 Exceptions to land reclamation act provisions.

MO Rev Stat § 444.766 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

Effective 28 Aug 2009

444.766. Exceptions to land reclamation act provisions. — 1. No provision of sections 444.760 to 444.790 shall apply to the excavation of minerals or fill dirt for the purposes of construction or land improvement as unrelated to the mining of minerals for a commercial purpose or reclamation of land subsequent to the surface mining of minerals.

2. No permit is required under sections 444.760 to 444.790 for the purpose of moving minerals or fill dirt within the confines of real property where excavation occurs, or for purposes of removing minerals or fill dirt from the real property as provided in this section.

(1) Excavations for construction pursuant to engineering plans and specifications prepared by an architect, professional engineer, or landscape architect licensed pursuant to chapter 327, or any excavation for construction performed under a written contract that requires excavation of minerals or fill dirt and establishes dates for completion of work and specifies the terms of payment for work, shall be presumed to be for the purposes of construction and shall not require a permit for surface mining.

(2) Excavations for purposes of land improvement where minerals removed from the site are excess minerals that cannot be used on-site for any practical purpose and at no time are subjected to crushing, screening, or other means of beneficiation with the exception of removal of dead trees, decaying vegetation, tree limbs, and stumps shall be presumed to be for the purposes of land improvement and shall not require a permit for surface mining, provided that:

(a) The site has not been designated as a surface mine by the federal Mine Safety and Health Administration;

(b) Minerals from the property are not used for commercial purposes on a frequent or ongoing basis; and

(c) A pit, peak, or ridge does not persist at the site as inconsistent with the purposes of land improvement.

(3) Permits shall not be required for the excavation of fill dirt, regardless of the site of disposition or whether construction occurs at the site of excavation.

3. (1) If the director or his or her designee determines that a surface mining permit is required for real property which is purported to be for purposes of construction or land improvement not requiring a surface mining permit under this section, such determination shall be sent in writing to the owner of the property by certified mail stating the reasons for such determination. Upon request of the person receiving the letter, an informal conference shall be scheduled with the director within fifteen calendar days to discuss the determination. Following the informal conference, the director shall issue a written determination regarding his or her findings of fact no later than thirty calendar days after the date of the conference. If the director agrees that a surface mining permit is required and the person disagrees with that decision, the person may make a written request for a hearing before the commission at its next regular meeting. Such written request shall be filed within thirty calendar days after receipt of the director's written determination, except when the thirtieth day would be later than the date of the next regularly scheduled commission meeting, the written request shall be filed at least seven days prior to the commission meeting unless the director and the person filing the request mutually agree to place the matter on the commission's agenda for a later meeting. The commission shall issue a written determination as to whether a surface mining permit is required under this state's law within thirty calendar days after the hearing. The written determination may be appealed as provided under this chapter.

(2) Until a final written determination has been issued under the process established under subdivision (1) of this subsection, the person receiving a letter stating the reasons a mining permit is required may continue activity at the site in dispute. The commission may stay the director's determination. If the final written determination is that a permit is required, all fees otherwise provided by statute or rules of the commission shall apply. If the determination is that no permit is required, no permit fees shall be required by the director or the commission.

(3) The process set out in this subsection for determining whether a mining permit is required shall not be subject to the hearing requirements of section 444.789.

­­--------

(L. 2005 H.B. 824, A.L. 2009 H.B. 246)

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 444.766 Exceptions to land reclamation act provisions.