Subdivision 1. Survey. The engineer shall proceed promptly to:

(1) examine the petition and order;

(2) make a preliminary survey of the area likely to be affected by the proposed drainage project to enable the engineer to determine whether the proposed drainage project is necessary and feasible with reference to the environmental, land use, and multipurpose water management criteria in section 103E.015, subdivision 1;

(3) examine and gather information related to determining whether the proposed drainage project substantially affects areas that are public waters; and

(4) if the proposed drainage project requires construction of an open channel, examine the nature and capacity of the outlet and any necessary extension.

Subd. 2. Limitation of survey. The engineer shall restrict the preliminary survey to the drainage area described in the petition, except that to secure an outlet the engineer may run levels necessary to determine the distance for the proper fall of the water. The preliminary survey must consider the impact of the proposed drainage project on the environmental, land use, and multipurpose water management criteria in section 103E.015, subdivision 1. The drainage authority may have other areas surveyed after:

(1) giving notice by mail of a hearing to survey additional areas, to be held at least ten days after the notice is mailed, to the petitioners and persons liable on the petitioners' bond;

(2) holding the hearing;

(3) obtaining consent of the persons liable on the petitioners' bond; and

(4) ordering the additional area surveyed by the engineer.

Subd. 3. Adopting federal project. The engineer may approve and include as a part of the report, a project of the United States relating to drainage or flood control that is within the proposed drainage project area, and may accept data, plats, plans, or information relating to the project furnished by United States engineers. The engineer does not need to make the preliminary survey if the material furnished by the United States is sufficient for the engineer to make the preliminary survey report.

Subd. 4. Preliminary survey report. The engineer shall report the proposed drainage project plan or recommend a different practical plan. The report must give sufficient information, in detail, to inform the drainage authority on issues related to feasibility, and show changes necessary to make the proposed plan practicable and feasible including extensions, laterals, and other work. If the engineer finds the proposed drainage project in the petition is feasible and complies with the environmental, land use, and multipurpose water management criteria in section 103E.015, subdivision 1, the engineer shall include in the preliminary survey report a preliminary plan of the drainage project showing the proposed ditches, tile, laterals, and other improvements, the outlet of the project, the watershed of the drainage project or system, and the property likely to be affected and its known owners. The plan must show:

(1) the elevation of the outlet and the controlling elevations of the property likely to be affected referenced to standard sea level datum, if practical;

(2) the probable size and character of the ditches and laterals necessary to make the plan practicable and feasible;

(3) the character of the outlet and whether it is sufficient;

(4) the probable cost of the drains and improvements shown on the plan;

(5) all other information and data necessary to disclose the practicability, necessity, and feasibility of the proposed drainage project;

(6) consideration of the drainage project under the environmental, land use, and multipurpose water management criteria in section 103E.015, subdivision 1; and

(7) other information as ordered by the drainage authority.

History: 1990 c 391 art 5 s 37; 2014 c 164 s 5-7

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 103E.245 — Preliminary Survey And Preliminary Survey Report.