Sec. 119.

(1) Except as otherwise provided by subsection (4), as between parties entitled to claim construction liens under this act, the liens have equal priority. This subsection applies and the construction liens have equal priority regardless of whether the lien arises at the time of the first actual physical improvement or at the time a notice is recorded under section 107a or 107b.

(2) A construction lien under this act has priority over all garnishments for the contract debt made after the lien arises, without regard to the date of recording of the claim of lien.

(3) A construction lien arising under this act has priority over all other interests, liens, or encumbrances that may attach to the building, structure, or improvement, or on the real property on which the building, structure, or improvement is erected, if the other interests, liens, or encumbrances are recorded after the construction lien arises.

(4) A mortgage, lien, encumbrance, or other interest recorded before the construction lien arises has priority over a construction lien arising under this act. The priority of the mortgage exists as to all obligations secured by the mortgage except for indebtedness arising out of advances made after the construction lien arises. An advance made pursuant to the mortgage, but after the construction lien arises, has priority over a construction lien if, for that advance, the mortgagee has received a contractor's sworn statement as provided in section 110, has made disbursements pursuant to the contractor's sworn statement, and has received waivers of lien from the contractor and all subcontractors, laborers, and suppliers who have provided notices of furnishing. The construction lien of a lien claimant not set forth on the sworn statement on which an advance was made is subordinate to the lien of the mortgage, including the advance, unless before the advance the lien claimant provided the designee with a notice of furnishing if required by section 109 or recorded a claim of lien. An advance made after a notice of furnishing has been provided or has been excused as provided in sections 108, 108a, and 109 or after a claim of lien has been recorded is subordinate to the construction lien of the lien claimant unless before the advance the mortgagee received from the lien claimant either a full unconditional waiver of lien or a partial unconditional waiver of lien for the full amount due the lien claimant as of the date through which the lien is waived as shown on the lien waiver and the date through which the lien is waived as shown on the partial unconditional waiver is within 30 days before the advance.

(5) For purposes of this section, retainage that is not payable under a contract until a certain event happens in addition to an improvement being provided, is not due as of the date the improvement is provided.

(6) For purposes of determining priorities under this section, a construction lien arises as follows:

(a) Except as provided in subdivision (b), at the time of the first actual physical improvement.

(b) As to a lien claimed by a person after the person has recorded a notice under section 107a or 107b, at the time a notice is recorded, subject to any applicable limitation under section 107a(4) or 107b(4).

History: 1980, Act 497, Eff. Jan. 1, 1982 ;-- Am. 1981, Act 191, Eff. Jan. 1, 1982 ;-- Am. 1982, Act 17, Eff. Mar. 1, 1982 ;-- Am. 2018, Act 367, Imd. Eff. Dec. 12, 2018

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 570.1119 Claims of Lien Having Equal Priority; Priority of Construction Lien Over Garnishments and Over Other Interests, Liens, or Encumbrances; Attachment; Effect of Recording; Priority of Recorded Mortgage, Lien, Encumbrance, or Other Interest Over Construction Lien; Advances; Retainage.