10 §1114. Contractor's and subcontractor's payment obligations

10 ME Rev Stat § 1114 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

§1114. Contractor's and subcontractor's payment obligations

Payment to a subcontractor for work is subject to the following conditions.   [PL 1993, c. 461, §1 (NEW).]

1.  Contractual agreements.  The contractor or subcontractor shall pay a subcontractor or material supplier strictly in accordance with the terms of the subcontractor's or material supplier's contract.

[PL 1993, c. 461, §1 (NEW).]

2.  Disclosure.  Notwithstanding any contrary agreement, a contractor or subcontractor shall disclose to a subcontractor or material supplier the due date for receipt of payments from the owner before a contract between those parties is entered. Notwithstanding any other provision of this chapter, if a contractor or subcontractor fails to accurately disclose the due date to a subcontractor or material supplier, the contractor or subcontractor is obligated to pay the subcontractor or material supplier as though the 20-day due dates in section 1113, subsection 3 were met.

[PL 2001, c. 471, Pt. A, §13 (AMD).]

3.  Invoices.  Notwithstanding any contrary agreement, when a subcontractor or material supplier has performed in accordance with the provisions of a contract, a contractor shall pay to the subcontractor or material supplier, and each subcontractor shall in turn pay to its subcontractors or material suppliers, the full or proportional amount received for each subcontractor's work and materials based on work completed or service provided under the subcontract, 7 days after receipt of each progress or final payment or 7 days after receipt of the subcontractor's or material supplier's invoice, whichever is later.

[PL 1993, c. 461, §1 (NEW).]

4.  Delayed payments.  Notwithstanding any contrary agreement, if any progress or final payment to a subcontractor or material supplier is delayed beyond the due date established in subsection 2 or 3, the contractor or subcontractor shall pay its subcontractor or material supplier interest on any unpaid balance due beginning on the next day, at an interest rate equal to that specified in Title 14, section 1602-C.

[PL 2003, c. 460, §2 (AMD).]

SECTION HISTORY

PL 1993, c. 461, §1 (NEW). PL 2001, c. 471, §A13 (AMD). PL 2003, c. 460, §2 (AMD).

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.