66-128n. Nuclear power generating facilities; decommissioning financing plan; hearings; approval or rejection of plan. (a) The state corporation commission shall hold a public hearing in accordance with the provisions of the Kansas administrative procedure act on each proposed decommissioning financing plan submitted under K.S.A. 66-128m and amendments thereto. The commission may hold such hearing in conjunction with rate proceedings filed by an owner of the facility.

(b) The commission shall approve such a plan if it finds that the licensee has provided reasonable assurances that: (1) The estimated time of closing of the nuclear power generating facility and the estimated cost of decommissioning are reasonable; (2) the licensee and the owners of the facility can adequately fund the decommissioning; (3) the share of the estimated cost of decommissioning for each owner of the facility is reasonable; (4) the plans and options for insuring against or otherwise financing any shortfall in decommissioning funds resulting from a premature closing are adequate and reasonable; (5) the owners are legally bound to accept their respective shares of the ultimate financial responsibility for decommissioning as provided under K.S.A. 66-128p and amendments thereto; and (6) the plan will periodically be reviewed and revised to reflect more closely the costs and available techniques for decommissioning. This update shall occur at least every five years.

(c) If the commission finds that the decommissioning plan does not meet the criteria under subsection (b), it shall reject the plan and order that it be modified as the commission deems necessary to meet such criteria.

History: L. 1985, ch. 225, § 57; L. 1988, ch. 356, § 229; July 1, 1989.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
66-128n Nuclear power generating facilities; decommissioning financing plan; hearings; approval or rejection of plan.