66-1,178 Same; siting of electric transmission lines; permit required; application, contents; hearings.

KS Stat § 66-1,178 (2018) (N/A)
Copy with citation
Copy as parenthetical citation

66-1,178. Same; siting of electric transmission lines; permit required; application, contents; hearings. (a) No electric utility may begin site preparation for or construction of an electric transmission line, or exercise the right of eminent domain to acquire any interest in land in connection with the site preparation for a construction of any such line without first acquiring a siting permit from the commission. Whenever any electric utility desires to obtain such a permit, the utility shall file an application with the commission setting forth therein that the utility proposes to construct an electric transmission line and specifying:

(1) The proposed location thereof;

(2) the names and addresses of the landowners of record whose land or interest therein is proposed to be acquired in connection with the construction of or is located within 660 feet of the center line of the easement where the line is proposed to be located; and

(3) such other information as may be required by the commission.

(b) Upon the filing of an application pursuant to subsection (a), the commission shall fix a time for a public hearing on such application, which shall be not more than 90 days after the date the application was filed, to determine the necessity for and the reasonableness of the location of the proposed electric transmission line. The commission shall fix the place for hearing, which shall be in one of the counties through which the electric transmission line is proposed to traverse.

(c) The commission may conduct an evidentiary hearing on an application filed pursuant to this section at such time and place as the commission deems appropriate.

(d) The commission shall issue a final order on the application within 120 days after the date the application was filed.

History: L. 1979, ch. 207, § 2; L. 1984, ch. 248, § 1; L. 2000, ch. 85, § 1; Apr. 20.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
66-1,178 Same; siting of electric transmission lines; permit required; application, contents; hearings.