8-1-2.4-6. Private generation projects; sale of excess output; interconnection

IN Code § 8-1-2.4-6 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

Sec. 6. (a) The owner of a private generation project may sell excess electric output generated by the private generation project to an electric utility as provided in subsection (b) to the extent the sale is consistent with applicable federal and state laws, rules, and regulations.

(b) An electric utility may purchase excess output described in subsection (a) from a private generation project that is located entirely in the assigned service area of the electric utility. The terms of the purchase must be consistent with the integrated resource plan filed with the commission by the electric utility under 170 IAC 4-7, including avoided energy and capacity costs determined in the integrated resource plan.

(c) An electric utility is entitled to recover costs associated with the purchase of energy and capacity under subsection (b) under IC 8-1-2-42(d).

(d) An electric utility shall interconnect with a private generation project upon request, subject to reasonable considerations of safety, reliability, and financial assurance. The interconnection of a private generation project with an electric utility's distribution system is governed by 170 IAC 4-4.3. The interconnection of a private generation project with an electric utility's transmission system is governed by federal law and regulation, including orders, regulations, and transmission tariffs approved by the Federal Energy Regulatory Commission.

(e) Upon the request of the owner of a private generation project, an electric utility shall provide the private generation project with back up, maintenance, and supplementary power. The electric utility shall charge rates that:

(1) are based on the electric utility's costs;

(2) do not discriminate against:

(A) the private generation project; or

(B) other customers of the electric utility with load characteristics similar to the private generation project; and

(3) do not create subsidies for:

(A) the private generation project; or

(B) retail customers of the electric utility.

As added by P.L.222-2014, SEC.4.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
8-1-2.4-6. Private generation projects; sale of excess output; interconnection