13-18-27-16. Time limit for review authority's preliminary determination of whether construction plan is substantially complete

IN Code § 13-18-27-16 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

Sec. 16. (a) A review authority to which a construction plan is submitted must make a preliminary determination whether the construction plan is substantially complete before the end of:

(1) the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site; or

(2) the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site.

(b) If a review authority to which a construction plan is submitted under subsection (a):

(1) makes a preliminary determination that the construction plan is substantially complete; and

(2) notifies the project site owner of its favorable preliminary determination;

before the end of the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, the project site owner may submit a notice of intent letter including the information required by 327 IAC 15-5-5 or the general permit and, forty-eight (48) hours after submission of the notice of intent letter, may begin the construction project, including the land disturbing activities of the construction project.

(c) If a review authority to which a construction plan for a small or very small construction activity site or a large construction activity site is submitted under subsection (a) does not notify the project site owner before the end of the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, of its preliminary determination as to whether the construction plan is substantially complete, the project site owner may submit a notice of intent letter including the information required by 327 IAC 15-5-5 or the general permit and, forty-eight (48) hours after submission of the notice of intent letter, may begin the construction project, including the land disturbing activities of the construction project.

(d) If a review authority to which a construction plan is submitted under subsection (a) notifies the project site owner before the end of the tenth working day after the day on which the construction plan is submitted to the review authority, in the case of a small or very small construction activity site, or the fourteenth working day after the day on which the construction plan is submitted to the review authority, in the case of a large construction activity site, of its preliminary determination that the construction plan is not substantially complete, the project site owner may not submit a notice of intent letter until the review authority makes a conclusive favorable determination concerning the construction plan under 327 IAC 15-5, the general permit, or the applicable ordinance of the MS4 community.

(e) If a review authority to which a construction plan is submitted under subsection (a):

(1) makes a preliminary determination that the construction plan is substantially complete; and

(2) makes a conclusive unfavorable determination concerning the construction plan under 327 IAC 15-5, the general permit, or the applicable ordinance of the MS4 community;

the land disturbing activities of the construction project must stop when the review authority notifies the project site owner of the review authority's conclusive unfavorable determination concerning the construction plan.

As added by P.L.248-2019, SEC.14.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
13-18-27-16. Time limit for review authority's preliminary determination of whether construction plan is substantially complete