LegalFix

Section 61-541 - BINDING RATEMAKING TREATMENTS APPLICABLE WHEN COSTS OF A NEW ELECTRIC GENERATION FACILITY ARE INCLUDED IN RATES.

ID Code § 61-541 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

61-541. BINDING RATEMAKING TREATMENTS APPLICABLE WHEN COSTS OF A NEW ELECTRIC GENERATION FACILITY ARE INCLUDED IN RATES. (1) As used in this section, "certificate" means a certificate of convenience and necessity issued under section 61-526, Idaho Code.

(2) A public utility that proposes to construct, lease or purchase an electric generation facility or transmission facility, or make major additions to an electric generation or transmission facility, may file an application with the commission for an order specifying in advance the ratemaking treatments that shall apply when the costs of the proposed facility are included in the public utility’s revenue requirements for ratemaking purposes. For purposes of this section, the requested ratemaking treatments may include nontraditional ratemaking treatments or nontraditional cost recovery mechanisms.

(a) In its application for an order under this section, a public utility shall describe the need for the proposed facility, how the public utility addresses the risks associated with the proposed facility, the proposed date of the lease or purchase or commencement of construction, the public utility’s proposal for cost recovery, and any proposed ratemaking treatments to be applied to the proposed facility.

(b) For purposes of this section, ratemaking treatments for a proposed facility include but are not limited to:

(i) The return on common equity investment or method of determining the return on common equity investment;

(ii) The depreciation life or schedule;

(iii) The maximum amount of costs that the commission will include in rates at the time determined by the commission without the public utility having the burden of moving forward with additional evidence of the prudence and reasonableness of such costs;

(iv) The method of handling any variances between cost estimates and actual costs; and

(v) The treatment of revenues received from wholesale purchasers of service from the proposed facility.

(3) The commission shall hold a public hearing on the application submitted by the public utility under this section. The commission may hold its hearing in conjunction with an application for a certificate.

(4) Based upon the hearing record, the commission shall issue an order that addresses the proposed ratemaking treatments. The commission may accept, deny or modify a proposed ratemaking treatment requested by the utility. In determining the proposed ratemaking treatments, the commission shall maintain a fair, just and reasonable balance of interests between the requesting utility and the utility’s ratepayers.

(a) In reviewing the application, the commission shall also determine whether:

(i) The public utility has in effect a commission-accepted integrated resource plan;

(ii) The services and operations resulting from the facility are in the public interest and will not be detrimental to the provision of adequate and reliable electric service;

(iii) The public utility has demonstrated that it has considered other sources for long-term electric supply or transmission;

(iv) The addition of the facility is reasonable when compared to energy efficiency, demand-side management and other feasible alternative sources of supply or transmission; and

(v) The public utility participates in a regional transmission planning process.

(b) The commission shall use its best efforts to issue the order setting forth the applicable ratemaking treatments prior to the date of the proposed lease, acquisition or commencement of construction of the facility.

(c) The ratemaking treatments specified in the order issued under this section shall be binding in any subsequent commission proceedings regarding the proposed facility that is the subject of the order, except as may otherwise be established by law.

(5) The commission may not require a public utility to apply for an order under this section.

(6) The commission may promulgate rules or issue procedural orders for the purpose of administering this section.

History:

[61-541, added 2009, ch. 145, sec. 1, p. 436.]

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 61-541 - BINDING RATEMAKING TREATMENTS APPLICABLE WHEN COSTS OF A NEW ELECTRIC GENERATION FACILITY ARE INCLUDED IN RATES.