LegalFix

§ 46-3A-7. Construction costs as part of rate base; review of construction work in progress; verification of expenditures; recovery of costs of canceled construction

GA Code § 46-3A-7 (2018) (N/A)
Copy with citation
Copy as parenthetical citation

(a) So long as the commission has not modified or revoked the certificate for an electric plant under Code Section 46-3A-6 and to the extent the utility seeks to add to its rate base upon completion of the plant construction costs that do not exceed 100 percent of those approved by the commission under Code Section 46-3A-5, Code Section 46-3A-6, or subsection (b) of this Code section, that construction cost amount may be excluded from the rate base only on the basis of fraud, concealment, failure to disclose a material fact, imprudence, or criminal misconduct. Inclusion of costs in excess of 100 percent of those approved by the commission shall not be permitted unless shown by the utility to have been reasonable and prudent.

(b) In addition to the review of the continuing need for an electric plant under construction prescribed in Code Section 46-3A-6, the commission, upon its own motion, may conduct or the utility may request that the commission conduct an ongoing review of such construction as it proceeds. Every one to three years, or at such lesser intervals upon the direction of the commission or request of the utility, the applicant shall file a progress report and any proposed revisions in the cost estimates, construction schedule, or project configuration. Within 180 days of such filing, the commission shall verify and approve or disapprove expenditures made pursuant to the certificate and shall approve, disapprove, or modify any proposed revisions. If the commission fails to so act within 180 days after such filing, the previous expenditures and any proposed revisions shall be deemed approved by operation of law.

(c) If the commission verifies expenditures as made pursuant to a certificated capacity resource, that verification forecloses subsequent exclusion of those costs from the utility's rate base, absent fraud, concealment, failure to disclose a material fact, imprudence, or criminal misconduct.

(d) If the commission disapproves of all or part of the proposed revisions and the utility cancels construction of some or all of the facility as a result of the disapproval, the utility may recover through any rate-making vehicle over a reasonable period of time, absent fraud, concealment, failure to disclose a material fact, imprudence, or criminal misconduct, the amount of its actual investment, net of actual salvage value, in the partially completed portion of the facility along with the cost of carrying the unamortized balance of that investment to the extent such investment is verified as made pursuant to the certificate.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
§ 46-3A-7. Construction costs as part of rate base; review of construction work in progress; verification of expenditures; recovery of costs of canceled construction