LegalFix

403.537 - Determination of need for transmission line; powers and duties.

FL Stat § 403.537 (2019) (N/A)
Copy with citation
Copy as parenthetical citation

(1)(a) Upon request by an applicant or upon its own motion, the Florida Public Service Commission shall schedule a public hearing, after notice, to determine the need for a transmission line regulated by the Florida Electric Transmission Line Siting Act, ss. 403.52-403.5365. The notice shall be published at least 21 days before the date set for the hearing and shall be published by the applicant in at least one-quarter page size notice in newspapers of general circulation, and by the commission in the manner specified in chapter 120, by giving notice to counties and regional planning councils in whose jurisdiction the transmission line could be placed, and by giving notice to any persons who have requested to be placed on the mailing list of the commission for this purpose. Within 21 days after receipt of a request for determination by an applicant, the commission shall set a date for the hearing. The hearing shall be held pursuant to s. 350.01 within 45 days after the filing of the request, and a decision shall be rendered within 60 days after such filing.

(b) The commission shall be the sole forum in which to determine the need for a transmission line. The need for a transmission line may not be raised or be the subject of review in another proceeding.

(c) In the determination of need, the commission shall take into account the need for electric system reliability and integrity, the need for abundant, low-cost electrical energy to assure the economic well-being of the residents of this state, the appropriate starting and ending point of the line, and other matters within its jurisdiction deemed relevant to the determination of need. The appropriate starting and ending points of the electric transmission line must be verified by the commission in its determination of need.

(d) The determination by the commission of the need for the transmission line, as defined in s. 403.522(22), is binding on all parties to any certification proceeding under the Florida Electric Transmission Line Siting Act and is a condition precedent to the conduct of the certification hearing prescribed therein. An order entered pursuant to this section constitutes final agency action.

(2) The commission shall have the following powers and duties:

(a) To adopt or amend reasonable procedural rules to implement the provisions of this section.

(b) To prescribe the form, content, and necessary supporting documentation and the required studies for the determination of need.

(3) Any time limitation in this section may be altered by the commission upon stipulation between the commission and the applicant or for good cause shown by any party.

History.—s. 3, ch. 80-65; s. 13, ch. 81-131; s. 19, ch. 83-222; s. 45, ch. 90-331; s. 66, ch. 2006-230.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
403.537 - Determination of need for transmission line; powers and duties.