(1)

(a) A utility is entitled to fully recover the costs that it prudently incurs in executing an approved emission reduction plan, including the costs of planning, developing, constructing, operating, and maintaining any emission control or replacement capacity constructed pursuant to the plan, as well as any interim air quality emission control costs the utility incurs while the plan is being implemented.

(b) The general assembly finds that the emissions reductions under this part 2 are being made to assist the state of Colorado to comply with current and reasonably foreseeable emission restrictions under federal law. To provide this assistance, the utility is being asked to make substantial capital investments and to enter into substantial contractual commitments in an expedited time period outside of the normal resource planning process.

(2)

(a) If a public utility's wholesale sales are subject to regulation by the federal energy regulatory commission, and if the public utility sells power on the wholesale market from a project developed pursuant to the plan, the commission shall determine whether to assign a portion of the plan cost to be recovered from the public utility's wholesale customers. The commission may make such assignment to the extent that it does not conflict with the public utility's wholesale contracts entered into before April 19, 2010.

(b) Except as specified in paragraph (c) of this subsection (2), if the commission makes an assignment of costs pursuant to paragraph (a) of this subsection (2) and if the utility applies to the federal energy regulatory commission for recovery and pursues that application in good faith, then:

(I) To the extent that the federal energy regulatory commission does not permit recovery of the allocated wholesale portion of plan-related investment, the commission shall approve retail rates sufficient to recover such disallowed wholesale portion of the investment through the recovery mechanism detailed in this section; and

(II) The public utility may not recover any revenue shortfall caused by a delay in making any filing with the federal energy regulatory commission or due to any rate suspension period employed by the federal energy regulatory commission or because the public utility failed to pursue recovery of the amounts at the federal energy regulatory commission in good faith.

(c) If the public utility fails to apply to the federal energy regulatory commission within six months after the commission's final order assigning a portion of the plan's costs to the public utility's wholesale customers, the public utility is not entitled to recover the assigned portion of the costs from its retail customers.

(3) Current recovery shall be allowed on construction work in progress at the utility's weighted average cost of capital, including its most recently authorized rate of return on equity, for expenditures on projects associated with the plan during the construction, startup, and preservice implementation phases of the projects.

(4) To the extent that an approved plan includes the early conversion or closure of coal-based generation capacity by January 1, 2015, and to the extent that the utility demonstrates that a lag in the recovery of the costs of the plan related to the investment required by such plan contributes to a utility earning less than its authorized return on equity, the commission shall employ rate-making mechanisms, in addition to allowing a current return on construction work in progress, that permit rate adjustments, no less frequently than once per year, without requiring the utility to file a general rate case to allow recovery of the approved plan's costs. Such rate-making mechanisms may include a separate rate adjustment clause, regular make-whole rate increases, or other appropriate mechanisms as determined by the commission.

(5) During the time any special regulatory practice is in effect, the utility shall file a new rate case at least every two years or file a base rate recovery plan that spans more than one year.

(6) The commission shall allow, but not require, the utility to develop and own as utility rate-based property any new electric generating plant constructed primarily to replace any coal-fired electric generating unit retired pursuant to the plan filed under this part 2.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
§ 40-3.2-207. Cost recovery - legislative declaration