(1) The commission shall promulgate such regulations as may be necessary and proper for the orderly and effective administration of construction permits and renewable operating permits. Such regulations shall be in conformity with the provisions of this article and with federal requirements, shall be in furtherance of the policy contained in section 25-7-102, and shall implement, where applicable, permit and permit application contents, procedures, requirements, and restrictions with respect to the following:

(a) Identification and address of the owner and operator of the source or facility from which the emission or emissions are to be permitted;

(b) Location, quantity, and quality characteristics of the permitted emissions;

(c) Inspection, monitoring, record-keeping, and reporting requirements consistent with standard procedures, methods, and requirements established by the division;

(d) Deadlines for submitting permit applications and compliance plans, which, for applications for renewable operating permits, shall be no later than twelve months after the source becomes subject to an approved permit program. Deadlines for submitting permit applications for renewal of renewable operating permits shall be consistent with the requirements for filing such applications promulgated under the federal act but in no event earlier than required under the federal act.

(e) Contents of compliance plans to be submitted with renewable operating permit applications, which shall include schedules of compliance and progress reports at least every six months;

(f) Annual certifications of facility compliance with permit requirements, with prompt reporting of deviations from permit requirements;

(g) Submission of pertinent plans and specifications for the facility or source from which the emission is to be permitted;

(h) Restrictions on transfers of the permit;

(i) Procedures to be followed in the event of expansion or modification of the source or facility from which the emission occurs, or change in the quality, quantity, or frequency of the emission;

(j) Duration of the permit and renewal procedures. The duration of construction permits shall be until the renewable operating permit is issued. The duration of renewable operating permits is five years.

(k) Procedures to terminate, modify, or revoke and reissue permits for cause; procedures to revise permits, prior to renewal or termination, to incorporate applicable standards and regulations adopted after the issuance of such permit as expeditiously as practicable, but not later than eighteen months after promulgation of the applicable requirement, or to incorporate otherwise applicable standards and regulations in the permit; except that no such revision shall be required if the effective date of the standards or regulation occurs after the permit term expires, such revision shall be treated as a permit renewal, and the defense established under subsection (3) of this section shall apply until the permit amendment is complete;

(l) Procedures for incorporating emission limitations and other requirements from an applicable implementation plan, and other applicable requirements, into new or renewed permits;

(m) Procedures for notifying other contiguous states whose air quality may be affected by the emissions or that are within fifty miles of the source and for submitting comments and recommendations regarding the proposed permit;

(n) Procedures for modifying or amending permits, and procedures for authorizing any change within a permitted facility without requiring a permit revision, so long as any such change is not a modification under any provision of subchapter I of the federal act, and any such change does not exceed the emissions allowable under the permit, and advance notice is given to the division and the administrator. Such advance notice shall be no earlier than that required under regulationspromulgated pursuant to the federal act. Failure of the division to respond by the day following the last day of such advance notice period allows the source to proceed with any such change.

(o) Procedures to make available to the public any permit application, compliance plan, permit, and monitoring or compliance report, subject to the provisions of section 25-7-119 (4). If an applicant is required to submit information entitled to protection from disclosure, the applicant may submit such information separately.

(p) Procedures for issuing general permits after notice and an opportunity for hearing, covering numerous similar sources;

(q) Procedures for issuing single permits for a facility with multiple sources; and

(r) Requirements for permit applications, including a standard application form and criteria for determining in a timely fashion the completeness of applications.

(2) The division shall examine applications for and may issue, suspend, revoke, modify, deny, and otherwise administer all permits required under this article. Such administration shall be in accordance with the provisions of this article and regulations promulgated by the commission.

(3) (a) Compliance with all renewable operating permit terms and conditions shall be deemed compliance with section 25-7-114.3 and shall be deemed compliance with other applicable provisions of this article if:

(I) The permit includes the applicable requirements of such provisions; or

(II) The division or commission, in acting on the permit application, makes a determination that such other provisions are not applicable, and the permit includes the determination or a concise summary thereof. Such other provisions as are not applicable in each permit shall be identified upon the request of the permittee.

(b) Nothing in paragraph (a) of this subsection (3) shall alter or affect:

(I) The provisions of section 25-7-112 or 25-7-113 or section 303 of the federal act;

(II) The liability of an owner or operator of a source for any violation of applicable requirements prior to or at the time of permit issuance.

(4) For any permitted sand and gravel operation or crushed stone quarry or oil and gas well operation, if a breakdown of equipment or changes in market conditions require any additional crusher or screen or skid-mounted compressor or glycol dehydrator to be brought onto a site, the air pollutant emission notice filed under section 25-7-114.1 shall also serve as an application for a permit under the provisions of this section to continue operations at such a site with alternative or additional equipment until such permit is issued stating emission limitations.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
§ 25-7-114.4. Permit applications - contents - rules