(1) Legislative declaration. The general assembly hereby finds and declares that:

(a) Hydroelectric energy is a reliable, affordable, and sustainable energy source and is the largest source of clean energy in the United States;

(b) As of 2005, there were sixty-two operating hydroelectric energy facilities throughout Colorado, with a combined capacity of one thousand one hundred sixty-two megawatts;

(c) According to a recent bureau of reclamation study, Colorado currently has more than thirty sites on which new hydroelectric energy facilities could be placed and a federal department of energy report identifies another eleven potential sites. If all of the identified sites were constructed, they could power over sixty-five thousand homes each year.

(d)

(I) To construct, operate, or maintain a nonfederal hydroelectric energy facility, a person must apply to FERC for a license or a license exemption if the facility is located on navigable waters in the United States, occupies lands of the United States, utilizes surplus water or water power from a United States government dam, or, under some circumstances, is located on a stream over which the United States congress has commerce clause jurisdiction;

(II) As part of FERC's licensing process, an applicant for a hydroelectric energy facility license or license exemption must meet specific prefiling consulting requirements, including a requirement to consult with relevant state agencies about the proposed project and to provide those agencies with an opportunity to comment on the application and request any studies that may be relevant to the proposed project;

(III) To promote the construction and operation of new hydroelectric energy facilities, the United States congress passed the "Hydropower Regulatory Efficiency Act of 2013", federal Public Law 113-23, as amended, which exempts certain hydroelectric energy facilities that have an installed capacity of fewer than ten thousand kilowatts from the licensing requirements and streamlines the approval process for hydroelectric energy facilities generally; and

(e) To further promote the construction and operation of new hydroelectric energy facilities in Colorado, the role of state agencies in consulting on a hydroelectric energy facility application for a federal license or license exemption should be streamlined. To that end, the general assembly designates the office as the coordinating state agency to facilitate the timely state agency review of a proposed project.

(2) Definitions. As used in this section, unless the context otherwise requires:

(a) "Applicant" means a person applying for a FERC license or license exemption for a hydroelectric energy facility.

(b) "FERC" means the federal energy regulatory commission.

(c) "Hydroelectric energy" means the generation and delivery to the interconnection meter of any source of electrical or mechanical energy by harnessing the kinetic energy of water. "Hydroelectric energy" includes pumped hydroelectricity, as defined in section 40-2-123 (3.2)(c)(II), C.R.S.

(d) "Office" means the Colorado energy office.

(3) Coordination of state agency review by the Colorado energy office. (a) An applicant in Colorado must contact, and submit relevant documentation to, the office for the purpose of obtaining state agency review of his or her FERC application, as required as part of the consultation requirements set forth in 18 C.F.R. 4.38 concerning FERC license and license exemption procedures.

(b) The office shall coordinate state agency review of the application by providing the following to all relevant state agencies with potential interest in the applicant's hydroelectric energy project:

(I) Notice via e-mail of the application;

(II) Electronic copies of any documentation received from the applicant;

(III) A general description of the FERC review process; and

(IV) The deadline by which the other state agencies must submit any comments about the application to the office. The office shall set a deadline that is sufficiently in advance of the expiration of the comment period provided for by FERC to allow the office to compile other agencies' comments and its own comments for timely submission to FERC.

(c) Upon the expiration of the deadline set by the office for other agencies to review an application, the office shall compile any comments from other agencies and its own comments and submit the comments to FERC before the expiration of the comment period established by FERC. Thereafter, the office shall serve as a liaison between FERC and the other state agencies concerning any discussion of the comments submitted.

(d) The office shall provide information on its website about the streamlined review process set forth in this section.

(e) The director of the office may establish guidelines concerning the process and deadlines for disseminating information to other state agencies and collecting other state agencies' comments.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
§ 24-38.5-108. State agency coordination of review of federal license and license exemption applications for hydroelectric energy projects - legislative declaration - definitions - guidelines