(a) An applicant for a geothermal powerplant may propose a site to be approved that will accommodate a potential maximum electric generating capacity in excess of the capacity being proposed for initial construction. In addition to the information concerning the initial powerplant and related facilities proposed for construction required pursuant to Section 25520, such application shall include all of the following, to the extent known:

(1) The number, type, and energy source of electric generating units which the site is proposed ultimately to accommodate and the maximum generating capacity for each unit.

(2) The projected installation schedule for each unit.

(3) The impact of the site, when fully developed, on the environment and public health and safety.

(4) The amount and sources of cooling water needed at the fully developed site.

(5) The general location and design of auxiliary facilities planned for each stage of development, including, but not limited to pipelines, transmission lines, waste storage and disposal facilites, switchyards, and cooling ponds, lakes, or towers.

(6) Such other information relating to the design, operation, and siting of the facility as the commission may by regulation require.

(b) If an application is filed pursuant to subdivision (a) which proposes a site to be approved which will accommodate a potential maximum electric generating capacity in excess of the capacity being proposed for initial construction, the commission may, in its decision pursuant to subdivision (a) of Section 25540.3, either certify only the initial facility or facilities proposed for initial construction or may certify the initial facility or facilities and find the site acceptable for additional generating capacity of the type tentatively proposed. The maximum allowable amount and type of such additional capacity shall be determined by the commission.

If the decision includes a finding that a particular site is suitable to accommodate a particular additional generating capacity, the site shall be designated a potential multiple facility site. The commission may, in determining the acceptability of a potential multiple facility site, specify conditions or criteria necessary to ensure that future additional facilities will not exceed the limitations of the site.

(Added by Stats. 1978, Ch. 1271.)

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 25540.3.