(a) The board shall require that every applicant for a Permit A have located within the State of Alabama a minimum of 30,000 (water gallon capacity) gallons storage capacity for liquefied petroleum gases. Class B-1 permit holders shall be required to have a minimum of 18,000 (water gallon capacity) gallons storage capacity of liquefied petroleum gas.

(b) If the required minimum storage consists of more than one container, then no storage container in any installation used to meet this requirement of the law shall be a size less than 6,000 gallon (water capacity) and the storage capacity required by this section of the law shall be within close proximity to the area serviced and used by the applicant to service the applicant's customers in the State of Alabama.

(c) The board shall require that such person shall submit plans for the proposed bulk storage facility to the office of the board and obtain approval by the administrator of such plans before construction is begun. All such facilities must be constructed according to rules and regulations of the board and the completed unit must have board approval before being used.

(d) If the holder of a Permit A or Permit B-1 submits plans to the board for a storage plant that shall remain the holder's property even though the plant be at a customer's site or if the plant to be built is to be used as part of the holder's own distribution system, then there will be no additional fees for approval and inspection of this facility; however, if this permit holder undertakes to install a bulk storage system of 5,000 gallons water capacity or more in single containers or in multi-container installation of an aggregate of 5,000 gallons water capacity, the holder must obtain approval for the location and for the plans from the administrator of the board before construction is begun. When plans for the bulk storage plant described above are submitted to the board for approval, a fee of two hundred dollars ($200) must be paid at the same time. This fee of two hundred dollars ($200) will cover examination of the plans and one site inspection. An additional fee of fifty dollars ($50) for each inspection trip to the site, that is required, shall be paid to the board before final approval is given for the facility to be used. These fees may be changed by the board.

LegalFix

Copyright ©2024 LegalFix. All rights reserved. LegalFix is not a law firm, is not licensed to practice law, and does not provide legal advice, services, or representation. The information on this website is an overview of the legal plans you can purchase—or that may be provided by your employer as an employee benefit or by your credit union or other membership group as a membership benefit.

LegalFix provides its members with easy access to affordable legal services through a network of independent law firms. LegalFix, its corporate entity, and its officers, directors, employees, agents, and contractors do not provide legal advice, services, or representation—directly or indirectly.

The articles and information on the site are not legal advice and should not be relied upon—they are for information purposes only. You should become a LegalFix member to get legal services from one of our network law firms.

You should not disclose confidential or potentially incriminating information to LegalFix—you should only communicate such information to your network law firm.

The benefits and legal services described in the LegalFix legal plans are not always available in all states or with all plans. See the legal plan Benefit Overview and the more comprehensive legal plan contract during checkout for coverage details in your state.

Use of this website, the purchase of legal plans, and access to the LegalFix networks of law firms are subject to the LegalFix Terms of Service and Privacy Policy.

We have updated our Terms of Service, Privacy Policy, and Disclosures. By continuing to browse this site, you agree to our Terms of Service, Privacy Policy, and Disclosures.
Section 9-17-107 - Requirements as to storage capacity; exemption; submission of plans; construction requirements; fees.